Permit: T02CM03696
Permit Details
Apply Date:
08/06/2002
Applicant:
REPP CONSTRUCTION ,
Description:
NEW:SFR
Contractors:
- REPP CONSTRUCTION ,
Permit Reviews
Permit Number - T02CM03696
Permit Status: Final
Permit Description: NEW:SFR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/06/2002 | RESIDENTIAL BLDG/ZONING/FLOOD/WWM | 10/08/2002 | COMPLETED |
| 11/05/2002 | RESUBMITTAL | 11/19/2002 | COMPLETED |
| 11/19/2002 | RESUBMITTAL | 11/26/2002 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T02CM03696
Permit Status: Final
Permit Description: NEW:SFR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/06/2002 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T02CM03696
Permit Description: NEW:SFR
Total Completed Inspections - 24
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/24/2003 | ELECTRIC - UFER | EDURAZO | Approved | IVRS - Inspection 0000* |
| 01/24/2003 | EXCAVATION/LAYOUT REBAR & ZON | EDURAZO | Approved | IVRS - Inspection 0000* |
| 01/27/2003 | STEM WALL/RETAINING WALL | JRIVA | Approved | IVRS - Inspection 0000* |
| 01/30/2003 | PLUMBING - ROUGH, SOIL | EDURAZO | Approved | IVRS - Inspection 0000* |
| 02/04/2003 | BUILDING PRE-SLAB | EDURAZO | Approved | IVRS - Inspection 0000* |
| 02/20/2003 | PLUMBING - SEWER HCS CONNECT | EDURAZO | Approved | IVRS - Inspection 0000* |
| 03/27/2003 | REINFORCED MASONRY PRE-GROUT | EDURAZO | Approved | IVRS - Inspection 0000* |
| 05/29/2003 | ROOF NAILING | EDURAZO | Approved | IVRS - Inspection 0000* |
| 05/29/2003 | EXT METAL CLIPS/EXT SHEATHING | EDURAZO | Approved | IVRS - Inspection 0000* |
| 06/30/2003 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | IVRS - Inspection 0000* |
| 06/30/2003 | ELECTRIC - TEMPORARY SERVICE | DQUINN | Approved | IVRS - Inspection 0000* |
| 06/30/2003 | ELECTRIC - CABLE DROP | DQUINN | Approved | IVRS - Inspection 0000* |
| 07/09/2003 | MECHANICAL - INTERMEDIATE | HCAMPBEL | Approved | IVRS - Inspection 0000* |
| 07/09/2003 | PLUMBING - GAS PRESSURE TEST | HCAMPBEL | Approved | IVRS - Inspection 0000* |
| 07/09/2003 | PLUMBING - INTERMEDIATE | HCAMPBEL | Approved | IVRS - Inspection 0000* |
| 07/09/2003 | ELECTRIC - INTERMEDIATE | HCAMPBEL | Approved | IVRS - Inspection 0000* |
| 07/09/2003 | FRAMING | HCAMPBEL | Approved | IVRS - Inspection 0000* |
| 07/16/2003 | SHEET ROCK NAILING | JRIVA | Approved | IVRS - Inspection 0000* |
| 07/16/2003 | U VALUE FOR WINDOW | JRIVA | Approved | IVRS - Inspection 0000* |
| 08/21/2003 | PERMIT FINALED | FGREER | Approved | |
| 08/21/2003 | MECHANICAL - FINAL | FGREER | Approved | IVRS - Inspection 0000* |
| 08/21/2003 | PLUMBING - FINAL | FGREER | Approved | IVRS - Inspection 0000* |
| 08/21/2003 | ELECTRIC - FINAL | FGREER | Approved | IVRS - Inspection 0000*SENT TO TEP ON 08/22AM |
| 08/21/2003 | BUILDING - FINAL | FGREER | Approved | IVRS - Inspection 0000* |