Permit: T02CM03255
Permit Details
Apply Date:
07/09/2002
Applicant:
JOHN NOE
Description:
ADDITION:FRONT FOYER & STORAGE:REPAIR GAS LINE
Permit Reviews
Permit Number - T02CM03255
Permit Status: Final
Permit Description: ADDITION:FRONT FOYER & STORAGE:REPAIR GAS LINE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/09/2002 | RESIDENTIAL BLDG/ZONING/FLOOD | 07/30/2002 | COMPLETED |
| 11/14/2002 | REVISION | 11/14/2002 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T02CM03255
Permit Status: Final
Permit Description: ADDITION:FRONT FOYER & STORAGE:REPAIR GAS LINE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/09/2002 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T02CM03255
Permit Description: ADDITION:FRONT FOYER & STORAGE:REPAIR GAS LINE
Total Completed Inspections - 15
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/07/2002 | EXCAVATION/LAYOUT REBAR & ZON | JRIVA | Approved | IVRS - Inspection 0000* |
| 08/16/2002 | ROOF NAILING | DBRITO | Approved | IVRS - Inspection 0000*/ 1) INCLUDING CLOSET |
| 09/20/2002 | MECHANICAL - INTERMEDIATE | DBRITO | Approved | IVRS - Inspection 0000* |
| 09/20/2002 | ELECTRIC - INTERMEDIATE | DBRITO | Approved | IVRS - Inspection 0000* |
| 09/20/2002 | FRAMING | DBRITO | Approved | IVRS - Inspection 0000* |
| 09/25/2002 | SHEET ROCK NAILING | DBRITO | Approved | IVRS - Inspection 0000* |
| 09/25/2002 | STUCCO MESH | DBRITO | Approved | IVRS - Inspection 0000* |
| 11/29/2002 | PERMIT FINALED | DBRITO | Approved | |
| 11/29/2002 | MECHANICAL - FINAL | DBRITO | Approved | IVRS - Inspection 0000* |
| 11/29/2002 | PLUMBING - GAS PRESS TEST FNL | DBRITO | Approved | IVRS - Inspection 0000* |
| 11/29/2002 | PLUMBING - GAS PRESSURE TEST | DBRITO | Approved | IVRS - Inspection 0000* |
| 11/29/2002 | ELECTRIC - FINAL | DBRITO | Approved | IVRS - Inspection 0000* |
| 11/29/2002 | BUILDING - FINAL | DBRITO | Approved | IVRS - Inspection 0000* |
| 11/29/2002 | BUILDING PRE-SLAB | DBRITO | Approved | IVRS - Inspection 0000* |
| 11/29/2002 | STEM WALL/RETAINING WALL | DBRITO | Approved | IVRS - Inspection 0000* |