Permit: T02CM02631
Permit Details
Apply Date:
05/29/2002
Applicant:
CAYLOR CONSTRUCTION COMPANY , RO
Description:
OFFICE:NEW
Contractors:
- CAYLOR CONSTRUCTION COMPANY , RO
Permit Reviews
Permit Number - T02CM02631
Permit Status: Final
Permit Description: OFFICE:NEW
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/29/2002 | 3RD PARTY REVIEW-COMMERCIAL | 07/12/2002 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T02CM02631
Permit Description: OFFICE:NEW
Total Completed Inspections - 35
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/06/2002 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection 0000* OK UFER 20' REBAR & WATER BOND UFER. |
| 08/20/2002 | STEM WALL/RETAINING WALL | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 08/20/2002 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 09/04/2002 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 09/25/2002 | REINFORCED MASONRY PRE-GROUT | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 10/07/2002 | PLUMBING - SEWER HCS CONNECT | TRINIVJR | Approved | IVRS - Inspection 0000* |
| 10/07/2002 | PLUMBING - ROUGH, SOIL | TRINIVJR | Approved | IVRS - Inspection 0000*1.) HCS CONNECTION IS OK 2.) 4" TRUNK LINE INTO BLDG. ONLY IS OK 3.) SOIL WATER TEST IS OK 4.) OK TO BACKFILL TRENCH. |
| 10/07/2002 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 10/07/2002 | EXT METAL CLIPS/EXT SHEATHING | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 10/24/2002 | STUCCO MESH | AMATHIES | Approved | IVRS - Inspection 0000* |
| 10/26/2002 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection 0000* |
| 11/04/2002 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 11/06/2002 | PLUMBING - TEMP POWER FOR TEST | FMCCLURE | Approved | IVRS - Inspection 0000* |
| 11/06/2002 | ELECTRIC - TEMP POWER FOR TEST | DSANTACR | Approved | IVRS - Inspection 0000*OK TO CLEAR TEMP POWER FOR TEST OK CABLE DROP. |
| 11/06/2002 | BUILDING - TEMP POWER FOR TEST | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 11/07/2002 | MECHANICAL - TEMP PWR FOR TEST | JMILITEL | Approved | IVRS - Inspection 0000* |
| 11/07/2002 | ELECTRIC - CABLE DROP | MCAPISTR | Approved | IVRS - Inspection 0000*SENT TO TEP ON 11/8/02 AT 9:15AM |
| 11/07/2002 | FRAMING | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 11/26/2002 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | |
| 11/26/2002 | SIGN - FINAL | JSONKIN | Approved | IVRS - Inspection 0000* |
| 11/26/2002 | FIRE - FINAL | JEGAN | Approved | IVRS - Inspection 0000* |
| 11/26/2002 | FIRE SPKLR - FINAL | JEGAN | Approved | IVRS - Inspection 0000* |
| 11/26/2002 | FIRE SPKLR - OH PIPING & HYDRO | JEGAN | Approved | IVRS - Inspection 0000* |
| 12/03/2002 | PERMIT FINALED | HLEYVA | Approved | |
| 12/03/2002 | NPPO - FINAL | PGILBERT | Approved | |
| 12/03/2002 | LANDSCAPE - FINAL | PGILBERT | Approved | |
| 12/03/2002 | ENGINEERING - FINAL | JBRUCKME | Approved | 1873 N. KOLB TEMPORARY C OF O, PENDING COMPLETION OF ROOF DRAINAGE REMEDIATION. |
| 12/03/2002 | ENGINEERING - FINAL | JBRUCKME | Approved | 1867 N. KOLB ELECTRICAL SERVICE PANEL ONLY. |
| 12/03/2002 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection 0000* |
| 12/03/2002 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection 0000* |
| 12/03/2002 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection 0000* |
| 12/03/2002 | BUILDING - FINAL | HLEYVA | Approved | IVRS - Inspection 0000* |
| 12/03/2002 | SHEET ROCK NAILING | HLEYVA | Approved | IVRS - Inspection 0000* |
| 12/03/2002 | U VALUE FOR WINDOW | HLEYVA | Approved | IVRS - Inspection 0000* |
| 12/04/2002 | PLUMBING - FINAL | TRINIVJR | Approved | IVRS - Inspection 0000*1.) PLBG FINAL IS OK 2.) OK FOR C OF O. |