Permit: T02CM02169
Permit Details
Apply Date:
04/29/2002
Applicant:
VINT, ROBERT WALTER
Description:
ADDITION:CLASSROOMS/OFFICES
Contractors:
- COBRE BUILDING SYSTEMS INC ,
Permit Reviews
Permit Number - T02CM02169
Permit Status: C of o
Permit Description: ADDITION:CLASSROOMS/OFFICES
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/29/2002 | 3RD PARTY REVIEW-COMMERCIAL | 05/20/2002 | COMPLETED |
07/10/2002 | REVISION | 07/17/2002 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T02CM02169
Permit Status: C of o
Permit Description: ADDITION:CLASSROOMS/OFFICES
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/29/2002 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T02CM02169
Permit Description: ADDITION:CLASSROOMS/OFFICES
Total Completed Inspections - 38
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/21/2002 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection 0000* |
05/22/2002 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection 0000* |
06/03/2002 | PLUMBING - ROUGH, SOIL | TRINIVJR | Approved | IVRS - Inspection 0000* 1.) SOIL WATER TEST IS OK 2.) P.O.C. OF NEW BLDG DRAIN TO EXSISTING BLDG. SEWER IS OK 3.) OK TO BACKFILL TRENCH. 4.) U.G. COPPER WATER LOOP IS OK. |
07/09/2002 | BUILDING ABOVE CEILING | AQUIROZ | Approved | |
07/24/2002 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection 0000* |
07/26/2002 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection 0000*DUCT OPENINGS THROUGH FIRE RATED CEILING WILL BE ELIMINATED OK TO SHEET ROCK. |
08/01/2002 | STUCCO MESH | AQUIROZ | Approved | IVRS - Inspection 0000* |
08/05/2002 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection 0000* |
08/14/2002 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | |
08/14/2002 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | |
08/15/2002 | ELECTRIC - TEMP POWER FOR TEST | DSANTACR | Approved | IVRS - Inspection 0000* |
08/15/2002 | BUILDING - TEMP POWER FOR TEST | AQUIROZ | Approved | IVRS - Inspection 0000* |
08/15/2002 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection 0000* |
08/15/2002 | U VALUE FOR WINDOW | AQUIROZ | Approved | IVRS - Inspection 0000* |
08/15/2002 | FRAMING | AQUIROZ | Approved | IVRS - Inspection 0000* |
08/15/2002 | REINFORCED MASONRY PRE-GROUT | AQUIROZ | Approved | IVRS - Inspection 0000* |
08/15/2002 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection 0000* |
08/15/2002 | STEM WALL/RETAINING WALL | AQUIROZ | Approved | IVRS - Inspection 0000* |
08/16/2002 | FIRE - FINAL | LTHOMAS | Approved | |
08/16/2002 | FIRE - ALARM FINAL | LTHOMAS | Approved | |
08/16/2002 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
08/16/2002 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
08/16/2002 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
08/16/2002 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
08/16/2002 | MECHANICAL - TEMP PWR FOR TEST | CWILLIAM | Approved | IVRS - Inspection 0000* |
08/22/2002 | ENGINEERING - FINAL | DROBERTS | Approved | |
10/31/2002 | PLUMBING - FINAL | TRINIVJR | Approved | IVRS - Inspection 0000* |
11/06/2002 | PERMIT FINALED | DSANTACR | Approved | |
11/06/2002 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | |
11/06/2002 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection 0000*OK C OF O. |
11/07/2002 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection 0000*VERIFIED LETTER OF APPEAL FOR EQUIPMENT WITHIN 10' OF EDGE OF ROOF. OK FOR C OF O. |
11/07/2002 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | |
11/07/2002 | PLUMBING - SEWER HCS CONNECT | TRINIVJR | Approved | |
11/07/2002 | PLUMBING - GAS PRESSURE TEST | TRINIVJR | Approved | |
11/07/2002 | PLUMBING - YARD WTR LINE/TEST | TRINIVJR | Approved | |
11/07/2002 | PLUMBING - ABOVE CEILING | TRINIVJR | Approved | |
11/07/2002 | PLUMBING - INTERMEDIATE | TRINIVJR | Approved | |
11/07/2002 | BUILDING - FINAL | AQUIROZ | Approved |