Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
C of o
Type:
MULTI FAMILY NEW
Address NEW:
2550 E RIVER RD 11
Apply Date:
12/10/2001
Applicant:
N/A
Description:
NEW: APARTMENTS
Contractors:
  • LECHNER CONSTRUCTION INC ,

Permit Reviews

Permit Number - T01CM05965
Permit Status: C of o
Permit Description: NEW: APARTMENTS
Start Date Submittal Complete Date Status  
04/24/2006 REVISION - - 2ND 05/01/2006 COMPLETED Review Details
06/12/2003 3RD PARTY REVIEW-REVISION/OTHER 07/07/2003 COMPLETED Review Details
06/22/2006 REVISION - - 3RD 07/17/2006 COMPLETED Review Details
10/08/2002 RESUBMITTAL 10/08/2002 COMPLETED Review Details
12/13/2001 3RD PARTY REVIEW-COMMERCIAL 10/08/2002 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T01CM05965
Permit Status: C of o
Permit Description: NEW: APARTMENTS
Total Outstanding Activity Conditions - 1
Date Name
12/10/2001 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T01CM05965
Permit Description: NEW: APARTMENTS
Total Completed Inspections - 39
Date Description Inspector Results Comments
12/20/2002 PLUMBING - ROUGH, SOIL TRINIVJR Approved 1.) SOIL WATER TEST IS OK
2.) BLDG. DRAIN IS STUBBED OUT @ TWO WAY C.O. ONLY.
3.) OK TO BACKFILL TRENCH.
03/29/2004 ELECTRIC - UFER MCAPISTR Approved IVRS - Inspection 0000*
12/22/2005 BUILDING - PROGRESS SLONG Approved SLABS ONLY-NO PROGRESS
12/23/2005 FRAMING AQUIROZ Approved IVRS - Inspection :
See detailed listing on site.| 999*NO PROGRESS
08/03/2006 EXCAVATION/LAYOUT REBAR & ZON AQUIROZ Approved IVRS - Inspection :*
09/05/2006 ROOF NAILING AQUIROZ Approved IVRS - Inspection :*
09/05/2006 EXT METAL CLIPS/EXT SHEATHING AQUIROZ Approved IVRS - Inspection :*
11/06/2006 PLUMBING - INTERMEDIATE RMYERS Approved IVRS - Inspection :*
1. FIRST FLOOR COMPLETE OK TO COVER ALL AREAS.
2. 2ND FLOOR - ONLY 1/3 OF DEVELOPED LENGTH MAY BE RUN IN HORIZONTAL POSITION (2" VENT APPROX. 35') OK
3. PVC DWV THRU ROOF OK
4. PEX OK
TUBS OK
FLANGES OK
5. OK TO COVER ALL AREAS
11/08/2006 PLUMBING - SEWER HCS CONNECT RMYERS Approved IVRS - Inspection :*
SEWER CONNECTION TO SDR35 MADE OK
OK TO COVER
11/21/2006 STUCCO MESH AQUIROZ Approved IVRS - Inspection :*
12/05/2006 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
12/06/2006 MECHANICAL - INTERMEDIATE CWILLIAM Approved IVRS - Inspection :*
12/18/2006 PLUMBING - YARD WTR LINE/TEST RMYERS Approved IVRS - Inspection :*
YARDWATER PIPING COVERED W/O INSPECTION
CONTRACTOR POTHOLED PIPING
CONNECTIONS LOOK OK
12/18/2006 ELECTRIC - CABLE DROP CCLEMENS Approved IVRS - Inspection :*
12/19/2006 TEP CLEARANCE - AM JWEATHER Approved CEC CLEARERD FOR #11 FOR ALL UNITS C. CLEMENS
12/29/2006 SHEET ROCK NAILING AQUIROZ Approved IVRS - Inspection :*
UNIT 104 1ST LAYER
09/24/2007 ELECTRIC - TEMPORARY SERVICE RJIROUDE Approved IVRS - Inspection :*
OK TO CLEAR - ECO
#11101, 11201, 11102, 11202, 11103, 11203, 11104, 11204, 11105, 11205, 11106, 11206
09/25/2007 TEP CLEARANCE - PM JWEATHER Approved ECO CLEARED FOR UNITS #11101-11106 & #11201-11206 PER R. JIROUDEK
11/01/2007 RIGHT OF WAY - FINAL MOTERO Approved
11/01/2007 MECHANICAL - FINAL MRAMBER Approved IVRS - Inspection :*
SEE BUILDING INSPECTOR FOR C.C
11/02/2007 NPPO - FINAL ACONNOR Approved
11/02/2007 FIRE - FINAL LTHOMAS Approved
11/02/2007 FIRE - ALARM FINAL LTHOMAS Approved
11/02/2007 SIGN - FINAL JYBARRA Approved
11/05/2007 ENGINEERING - FINAL MRUSSO Approved
11/06/2007 ELECTRIC - FINAL CCLEMENS Approved IVRS - Inspection :*
11/06/2007 ELECTRIC - UNDERGROUND CCLEMENS Approved IVRS - Inspection :*
11/06/2007 ELECTRIC - INTERMEDIATE CCLEMENS Approved IVRS - Inspection :*
11/06/2007 ELECTRIC - ABOVE CEILING CCLEMENS Approved IVRS - Inspection :*
11/09/2007 FIRE SPKLR - FINAL LTHOMAS Approved
11/09/2007 FIRE SPKLR - OH PIPING & HYDRO LTHOMAS Approved
11/09/2007 FIRE SPKLR - UG PIPING FLUSH LTHOMAS Approved
11/09/2007 FIRE SPKLR - UG, PIPING, HYDRO LTHOMAS Approved
11/20/2007 PLUMBING - ABOVE CEILING RMYERS Approved PER PL FINAL
11/20/2007 BUILDING PRE-SLAB JBURGE Approved PER BU FINAL
11/20/2007 U VALUE FOR WINDOW JBURGE Approved PER BU FINAL
11/20/2007 BUILDING - FINAL JBURGE Approved IVRS - Inspection :*
11/20/2007 PLUMBING - FINAL RMYERS Approved IVRS - Inspection :*
1) PLUMBING FINAL OK
2) OK FOR C OF O S.T.O.I.
11/21/2007 PERMIT FINALED LJACKSON Approved

Documents

File Name Document Type  
C OF O_11-21-2007 CERT OF OCC VIEW
TEMP C OF O_11-09-2007.TIF CERT OF OCC VIEW
LAYOUTS&ENGINEERING.TIF DOCUMENTS VIEW
TRUSSSPECS.TIF DOCUMENTS VIEW
None DOCUMENTS VIEW