Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T01CM04309
Permit Details
Apply Date:
08/31/2001
Applicant:
CHESTNUT CONSTRUCTION CORPORATIO
Description:
NEW:OFFICE BUILDING
Contractors:
- CHESTNUT CONSTRUCTION CORPORATIO
Permit Reviews
Permit Number - T01CM04309
Permit Status: C of o
Permit Description: NEW:OFFICE BUILDING
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/31/2001 | 3RD PARTY REVIEW-COMMERCIAL | 11/01/2001 | COMPLETED |
08/31/2001 | SITE | 11/01/2001 | COMPLETED |
11/15/2001 | REVISION | 11/26/2001 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T01CM04309
Permit Status: C of o
Permit Description: NEW:OFFICE BUILDING
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
08/31/2001 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T01CM04309
Permit Description: NEW:OFFICE BUILDING
Total Completed Inspections - 31
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/19/2001 | STEM WALL/RETAINING WALL | EMONAHAN | Approved | IVRS - Inspection 0000$PA @ ELEVATOR |
12/24/2001 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | BLD LOCKED. |
12/27/2001 | PLUMBING - ROUGH, SOIL | JSTANLEY | Approved | IVRS - Inspection 0000*WRAP ALL ABS IN CONCRETE COPPER UNDER SLAB OK. |
12/27/2001 | ELECTRIC - UFER | RHOLLAND | Approved | IVRS - Inspection 0000* |
12/27/2001 | BUILDING PRE-SLAB | DWITT | Approved | |
12/27/2001 | EXCAVATION/LAYOUT REBAR & ZON | DWITT | Approved | |
12/30/2001 | ELECTRIC - UNDERGROUND | RHOLLAND | Approved | IVRS - Inspection 0000*OK 4-FLOOR BOXES OK STUBS DATA & POWER. |
03/08/2002 | ROOF NAILING | AMATHIES | Approved | IVRS - Inspection 0000* |
04/11/2002 | PLUMBING - SEWER HCS CONNECT | JSTANLEY | Approved | IVRS - Inspection 0000*TEST OK ON 8" FROM M-H TO STREET. |
05/01/2002 | PLUMBING - INTERMEDIATE | JSTANLEY | Approved | IVRS - Inspection 0000*2ND FLOOR TEST OK. |
06/07/2002 | FRAMING | AMATHIES | Approved | IVRS - Inspection 0000* |
06/12/2002 | MECHANICAL - TEMP PWR FOR TEST | CWILLIAM | Approved | |
06/13/2002 | ELECTRIC - TEMP POWER FOR TEST | RHOLLAND | Approved | IVRS - Inspection 0000* |
06/21/2002 | U VALUE FOR WINDOW | AMATHIES | Approved | IVRS - Inspection 0000* |
06/21/2002 | BUILDING ABOVE CEILING | AMATHIES | Approved | IVRS - Inspection 0000* |
06/28/2002 | FIRE - FINAL | LTHOMAS | Approved | |
06/28/2002 | FIRE SPKLR - FINAL | LTHOMAS | Approved | TEMP C/O ONLY |
07/02/2002 | MECHANICAL - ABOVE CEILING | CWILLIAM | Approved | |
07/02/2002 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | |
07/03/2002 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | |
07/03/2002 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection 0000* |
07/05/2002 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection 0000*OK OFFICE FURNITURE CONNECTIONS OK PVC TO PARKING STRUCTURE. |
07/11/2002 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection 0000*1.) PLEASE WEATHER PROOF CONNECTIONS IN PULL BOX.2.) POLES AT SOUTH WEST SIDE WILL BE INSTALLED ON PHASE II. |
07/12/2002 | ELECTRIC - CABLE DROP | RHOLLAND | Approved | |
07/15/2002 | SIGN - FINAL | JSONKIN | Approved | IVRS - Inspection 0000* |
08/29/2002 | PERMIT FINALED | PGILBERT | Approved | |
08/29/2002 | PLUMBING - FINAL | JSTANLEY | Approved | IVRS - Inspection 0000$ |
08/29/2002 | PLUMBING - YARD WTR LINE/TEST | JSTANLEY | Approved | |
08/30/2002 | BUILDING - FINAL | AMATHIES | Approved | IVRS - Inspection 0000* |
08/30/2002 | SHEET ROCK NAILING | AMATHIES | Approved | |
09/16/2002 | ENGINEERING - FINAL | DROBERTS | Approved |