Permit: T01CM04232
Permit Details
Apply Date:
08/28/2001
Applicant:
MACIAS GENERAL CONTRACTORS
Description:
SFR:TD#15-21-62
Contractors:
- MACIAS GENERAL CONTRACTORS
Permit Reviews
Permit Number - T01CM04232
Permit Status: C of o
Permit Description: SFR:TD#15-21-62
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/28/2001 | RESIDENTIAL BLDG/ZONING/FLOOD | 08/29/2001 | COMPLETED |
| 09/19/2001 | REVISION | 09/26/2001 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T01CM04232
Permit Status: C of o
Permit Description: SFR:TD#15-21-62
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/28/2001 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T01CM04232
Permit Description: SFR:TD#15-21-62
Total Completed Inspections - 25
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/01/2001 | PLUMBING - YARD WTR LINE/TEST | DBRITO | Approved | IVRS - Inspection 0000* |
| 10/01/2001 | PLUMBING - ROUGH, SOIL | DBRITO | Approved | IVRS - Inspection 0000* |
| 10/01/2001 | ELECTRIC - UFER | DBRITO | Approved | IVRS - Inspection 0000* |
| 10/01/2001 | EXCAVATION/LAYOUT REBAR & ZON | DBRITO | Approved | IVRS - Inspection 0000*/ 1) MASTER BATHROOM PLUMBING FOR SHOWER WAS CUT TO MOVE AWAY FROM STEM WALL RECALL FOR RE-INSPECTION FOR WATER TEST BEFORE PRE-SLAB |
| 10/04/2001 | STEM WALL/RETAINING WALL | HPEDROZA | Approved | IVRS - Inspection 0000* |
| 10/12/2001 | BUILDING PRE-SLAB | DBRITO | Approved | IVRS - Inspection 0000*/ 1) PROTECT PLUMBING WITH FOAM WRAP PRIOR TO POURING CONCRETE |
| 10/24/2001 | PLUMBING - SEWER HCS CONNECT | DBRITO | Approved | IVRS - Inspection 0000* |
| 11/07/2001 | ELECTRIC - TEMPORARY SERVICE | DBRITO | Approved | IVRS - Inspection 0000* |
| 11/07/2001 | ELECTRIC - CABLE DROP | DBRITO | Approved | IVRS - Inspection 0000* |
| 11/07/2001 | REINFORCED MASONRY PRE-GROUT | DBRITO | Approved | IVRS - Inspection 0000* |
| 12/27/2001 | ROOF NAILING | DBRITO | Approved | 1) EXPOSE ROOF TO VERIFY NAILING DRIED IN WITHOUT INSPECTION 2) STUCCO MESH AT GABLE ENDS REQUIRE INSPECTION, EXPOSE TO VERIFY MOISTURE BARRIER |
| 01/24/2002 | MECHANICAL - INTERMEDIATE | DBRITO | Approved | IVRS - Inspection 0000* |
| 01/24/2002 | PLUMBING - GAS PRESSURE TEST | DBRITO | Approved | IVRS - Inspection 0000* |
| 01/24/2002 | PLUMBING - INTERMEDIATE | DBRITO | Approved | IVRS - Inspection 0000* |
| 01/24/2002 | ELECTRIC - INTERMEDIATE | DBRITO | Approved | IVRS - Inspection 0000* |
| 01/24/2002 | FRAMING | DBRITO | Approved | IVRS - Inspection 0000* |
| 03/05/2002 | SHEET ROCK NAILING | DBRITO | Approved | IVRS - Inspection 0000* |
| 03/05/2002 | U VALUE FOR WINDOW | DBRITO | Approved | IVRS - Inspection 0000* |
| 03/05/2002 | STUCCO MESH | DBRITO | Approved | |
| 06/20/2002 | PERMIT FINALED | DBRITO | Approved | |
| 06/20/2002 | MECHANICAL - FINAL | DBRITO | Approved | IVRS - Inspection 0000* |
| 06/20/2002 | PLUMBING - FINAL | DBRITO | Approved | IVRS - Inspection 0000* |
| 06/20/2002 | PLUMBING - GAS PRESS TEST FNL | DBRITO | Approved | IVRS - Inspection 0000* |
| 06/20/2002 | ELECTRIC - FINAL | DBRITO | Approved | IVRS - Inspection 0000* |
| 06/20/2002 | BUILDING - FINAL | DBRITO | Approved | IVRS - Inspection 0000* |