Permit: T01CM04024
Permit Details
Apply Date:
08/16/2001
Applicant:
METRO PERMIT EXPRESS
Description:
TI:OFFICE
Contractors:
- CHESTNUT CONSTRUCTION CORPORATIO
Permit Reviews
Permit Number - T01CM04024
Permit Status: C of o
Permit Description: TI:OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/16/2001 | 3RD PARTY COMMERCIAL TI | 08/23/2001 | COMPLETED |
09/18/2001 | REVISION | 09/24/2001 | COMPLETED |
09/27/2001 | REVISION | 09/28/2001 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T01CM04024
Permit Status: C of o
Permit Description: TI:OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
08/16/2001 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T01CM04024
Permit Description: TI:OFFICE
Total Completed Inspections - 27
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/17/2001 | FRAMING | DWITT | Approved | IVRS - Inspection 0000* |
09/19/2001 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection 0000* |
09/19/2001 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection 0000* |
09/19/2001 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection 0000*1.) NO YARDWATER ON THIS CONTRACT. 2.) NO SEWER/HCS CONNECTION ON THIS CONTRACT 3.) PLUMBING INTERMEDIATE OK N/H DWV OK COPPER PIPE OK RECIRCULATION LINE OK 4.) OK TO COVER WALLS. |
09/20/2001 | SHEET ROCK NAILING | DWITT | Approved | IVRS - Inspection 0000* |
10/03/2001 | MECHANICAL - TEMP PWR FOR TEST | JMILITEL | Approved | OK FOR PARTIAL CEILING TILES IN WEST END OF 2ND FLOOR. |
10/03/2001 | PLUMBING - TEMP POWER FOR TEST | RMYERS | Approved | IVRS - Inspection 0000* |
10/03/2001 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection 0000*1.) ABOVE CEILING OK OK FOR TILE. |
10/03/2001 | BUILDING - TEMP POWER FOR TEST | DWITT | Approved | IVRS - Inspection 0000* |
10/03/2001 | BUILDING ABOVE CEILING | DWITT | Approved | IVRS - Inspection 0000* |
10/08/2001 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection 0000*OK TO COVER CEILINGS |
10/09/2001 | PLUMBING - FINAL | TRINIVJR | Approved | IVRS - Inspection 0000*1.) PLBG FINAL IS OK 2.) OK FOR C OF O. |
10/10/2001 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection 0000*OK FOR C OF O. |
10/10/2001 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection 0000* |
10/11/2001 | FIRE - FINAL | FIRE | Approved | |
10/12/2001 | ENGINEERING - FINAL | DROBERTS | Approved | |
10/12/2001 | ENGINEERING - FINAL | DROBERTS | Approved | Approved for Temporary Certificate of Occupancy at this time. |
10/24/2001 | ELECTRIC - FINAL | MCAPISTR | Approved | IVRS - Inspection 0000* |
10/24/2001 | ELECTRIC - ABOVE CEILING | MCAPISTR | Approved | IVRS - Inspection 0000* |
10/24/2001 | ELECTRIC - INTERMEDIATE | MCAPISTR | Approved | IVRS - Inspection 0000* |
10/25/2001 | RIGHT OF WAY - FINAL | ENGINEER | Approved | PER FALLEN 3RD FLOOR |
10/25/2001 | BUILDING - FINAL | DWITT | Approved | IVRS - Inspection 0000* |
10/26/2001 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | |
10/26/2001 | PERMIT FINALED | EMONAHAN | Approved | |
10/26/2001 | FIRE SPKLR - FINAL | FIRE | Approved | |
10/26/2001 | ELECTRIC - TEMP POWER FOR TEST | MCAPISTR | Approved | |
10/26/2001 | ELECTRIC - TEMPORARY SERVICE | MCAPISTR | Approved |