Permit: T01CM00322
Permit Details
Apply Date:
01/22/2001
Applicant:
METRO PERMIT EXPRESS, INC
Description:
NEW:SHELL BUILDING #2
Architects:
- SWAN WAYNE E
Contractors:
- CHESTNUT CONSTRUCTION CORPORATIO
Permit Reviews
Permit Number - T01CM00322
Permit Status: Final
Permit Description: NEW:SHELL BUILDING #2
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/22/2001 | 3RD PARTY REVIEW-COMMERCIAL | 04/23/2001 | COMPLETED |
03/20/2001 | REVISION | 04/10/2001 | COMPLETED |
08/14/2001 | REVISION | 08/16/2001 | COMPLETED |
09/05/2001 | REVISION | 09/17/2001 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T01CM00322
Permit Description: NEW:SHELL BUILDING #2
Total Completed Inspections - 31
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/18/2001 | EXCAVATION/LAYOUT REBAR & ZON | EMONAHAN | Approved | IVRS - Inspection 0000* |
05/23/2001 | STEM WALL/RETAINING WALL | DWITT | Approved | IVRS - Inspection 0000* |
05/31/2001 | PLUMBING - ROUGH, SOIL | FMCCLURE | Approved | IVRS - Inspection 0000*WASTE AND VENT TESTED TO 42". |
06/04/2001 | BUILDING PRE-SLAB | EMONAHAN | Approved | IVRS - Inspection 0000* |
06/06/2001 | PLUMBING - SEWER HCS CONNECT | FMCCLURE | Approved | IVRS - Inspection 0000* |
07/06/2001 | REINFORCED MASONRY PRE-GROUT | DWITT | Approved | IVRS - Inspection 0000* |
07/20/2001 | ROOF NAILING | LHANLY | Approved | IVRS - Inspection 0000* |
09/18/2001 | PLUMBING - ABOVE CEILING | FMCCLURE | Approved | IVRS - Inspection 0000* |
09/28/2001 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection 0000* |
09/28/2001 | BUILDING ABOVE CEILING | AMATHIES | Approved | IVRS - Inspection 0000* |
10/04/2001 | ELECTRIC - ABOVE CEILING | MCAPISTR | Approved | THIS IS AN OPEN CIELING SHELL ONLY SUBJECT TO NEW PERMIT FOR FINAL T.I. |
10/22/2001 | PLUMBING - FINAL | FMCCLURE | Approved | IVRS - Inspection 0000* |
10/22/2001 | U VALUE FOR WINDOW | LHANLY | Approved | IVRS - Inspection 0000* |
10/22/2001 | FRAMING | LHANLY | Approved | IVRS - Inspection 0000* |
10/23/2001 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection 0000* |
10/23/2001 | BUILDING - FINAL | LHANLY | Approved | IVRS - Inspection 0000*OK FOR TEMP POWER & TEMP C OF O. |
10/24/2001 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection 0000* |
10/24/2001 | ENGINEERING - FINAL | DROBERTS | Approved | TEMPORARY C OF O APPROVED AT THIS TIME, FINAL WILL NOT BE GIVEN UNTIL ALL ENGINEERING , AND DRAINAGE ITEMS ARE COMPLETE AND APPROVED |
10/24/2001 | ELECTRIC - CABLE DROP | MCAPISTR | Approved | IVRS - Inspection 0000* |
10/24/2001 | ELECTRIC - UFER | MCAPISTR | Approved | IVRS - Inspection 0000* |
10/25/2001 | NPPO - FINAL | JLINVILL | Approved | OK FOR TEMP C/O |
10/25/2001 | LANDSCAPE - FINAL | JLINVILL | Approved | OK for temp. C of O. |
10/30/2001 | ELECTRIC - FINAL | MCAPISTR | Approved | IVRS - Inspection 0000* |
02/01/2002 | FIRE SPKLR - FINAL | FIRE | Approved | |
02/01/2002 | FIRE SPKLR - OH PIPING & HYDRO | FIRE | Approved | |
02/01/2002 | FIRE SPKLR - UG PIPING FLUSH | FIRE | Approved | |
02/05/2002 | PERMIT FINALED | LHANLY | Approved | |
02/05/2002 | MECHANICAL - TEMP PWR FOR TEST | LHANLY | Approved | |
02/05/2002 | PLUMBING - TEMP POWER FOR TEST | LHANLY | Approved | |
02/05/2002 | ELECTRIC - TEMP POWER FOR TEST | LHANLY | Approved | |
02/05/2002 | BUILDING - TEMP POWER FOR TEST | LHANLY | Approved |