Permit: T01CM00102
Permit Details
Status:
C of o
Type:
COMMERCIAL NEW
Address:
3134 N FREEWAY INDUSTRIAL LP
Address NEW:
3134 N FREEWAY INDUSTRIAL LP
Apply Date:
01/05/2001
Applicant:
J R TUTTLE CO
Description:
DISTRIBUTION CENTER/OFFICE
Contractors:
- J R TUTTLE CO
Permit Reviews
Permit Number - T01CM00102
Permit Status: C of o
Permit Description: DISTRIBUTION CENTER/OFFICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/05/2001 | 3RD PARTY REVIEW-COMMERCIAL | 02/13/2001 | COMPLETED |
| 01/25/2001 | SITE | 02/13/2001 | COMPLETED |
| 02/13/2001 | RESUBMITTAL | 02/13/2001 | COMPLETED |
| 02/13/2001 | RESUBMITTAL | 02/13/2001 | COMPLETED |
| 10/04/2001 | REVISION | 10/10/2001 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T01CM00102
Permit Description: DISTRIBUTION CENTER/OFFICE
Total Completed Inspections - 24
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/20/2001 | PLUMBING - ROUGH, SOIL | JSTANLEY | Approved | IVRS - Inspection 0000* |
| 03/15/2001 | ELECTRIC - UFER | RHOLLAND | Approved | IVRS - Inspection 0000* |
| 05/29/2001 | REINFORCED MASONRY PRE-GROUT | EMONAHAN | Approved | IVRS - Inspection 0000* |
| 06/24/2001 | PLUMBING - GAS PRESSURE TEST | RMYERS | Approved | IVRS - Inspection 0000* |
| 06/26/2001 | PLUMBING - INTERMEDIATE | JSTANLEY | Approved | IVRS - Inspection 0000* |
| 08/29/2001 | BUILDING - TEMP POWER FOR TEST | EMONAHAN | Approved | IVRS - Inspection 0000* |
| 08/30/2001 | MECHANICAL - TEMP PWR FOR TEST | CWILLIAM | Approved | IVRS - Inspection 0000* |
| 08/30/2001 | ELECTRIC - TEMP POWER FOR TEST | RMAJUTA | Approved | IVRS - Inspection 0000*OK TO CLEAR TEMP POWER |
| 09/11/2001 | PLUMBING - TEMP POWER FOR TEST | RMYERS | Approved | OK FOR TEMP POWER S.T.O.I. |
| 09/12/2001 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection 0000* |
| 09/26/2001 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection 0000* |
| 09/26/2001 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection 0000*OK FINAL. |
| 10/24/2001 | ENGINEERING - FINAL | DROBERTS | Approved | |
| 10/30/2001 | PLUMBING - FINAL | JSTANLEY | Approved | IVRS - Inspection 0000*REVISED PLAN ON JOB TESTING ON BACKFLOW DEVICES COMPLETE LAST INSP ON JOB PLEASE PROVIDE GAS CARD. |
| 10/31/2001 | BUILDING - FINAL | EMONAHAN | Approved | IVRS - Inspection 0000$LEFT GAS CARD. |
| 10/31/2001 | FRAMING | EMONAHAN | Approved | |
| 10/31/2001 | BUILDING PRE-SLAB | EMONAHAN | Approved | |
| 10/31/2001 | STEM WALL/RETAINING WALL | EMONAHAN | Approved | |
| 10/31/2001 | EXCAVATION/LAYOUT REBAR & ZON | EMONAHAN | Approved | |
| 11/06/2001 | FIRE - HYDRANTS | FIRE | Approved | |
| 11/06/2001 | FIRE SPKLR - OH PIPING & HYDRO | FIRE | Approved | |
| 11/06/2001 | FIRE SPKLR - UG PIPING FLUSH | FIRE | Approved | |
| 11/09/2001 | RIGHT OF WAY - FINAL | ENGINEER | Approved | |
| 12/27/2001 | PERMIT FINALED | EMONAHAN | Approved |