Permit: T00CM02389
Permit Details
Apply Date:
05/09/2000
Applicant:
SWINERTON AND WALBERG CO
Description:
TI:OPERATING ROOM & STG
Contractors:
- SWINERTON AND WALBERG CO
Permit Reviews
Permit Number - T00CM02389
Permit Status: C of o
Permit Description: TI:OPERATING ROOM & STG
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/08/2001 | 3RD PARTY REVIEW-COMMERCIAL | 09/04/2001 | STOPPED |
08/21/2000 | COMMERCIAL TI | 08/25/2000 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T00CM02389
Permit Description: TI:OPERATING ROOM & STG
Total Completed Inspections - 15
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/29/2000 | PLUMBING - INTERMEDIATE | TRINIVJR | Approved | |
08/29/2000 | PLUMBING - ROUGH, SOIL | TRINIVJR | Approved | |
10/27/2000 | SHEET ROCK NAILING | AMATHIES | Approved | IVRS - Inspection 0000* RMS 111, THRU 117 |
10/27/2000 | FRAMING | AMATHIES | Approved | IVRS - Inspection 0000* AMS 111-117 |
11/15/2000 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection 0000* OK TO PROCEED |
11/15/2000 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection 0000* OK TO INSULATE HOT WATER PIPE |
11/28/2000 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection 0000* INSPECTION ON PHASE I IMAGING OK FOR TEMP C OF O |
11/28/2000 | BUILDING - FINAL | AMATHIES | Approved | IVRS - Inspection 0000* OK TEMP C OF O PHASE I NUC. MED. MAMMO |
11/28/2000 | BUILDING ABOVE CEILING | AMATHIES | Approved | |
11/29/2000 | PLUMBING - ABOVE CEILING | TRINIVJR | Approved | |
12/01/2000 | SIGN - FINAL | JSONKIN | Approved | IVRS - Inspection 0000* |
12/01/2000 | ELECTRIC - FINAL | DSANTACR | Approved | 1.) #7106 HAS BORNT OR SHORTED OUT METER CLIP 2.) OWNERS SOCKET CONTACTS AND TERMINATION TO BE CLEANED 3.) LABEL OWNERS METER AND PANEL 4.) IDENTIFY NEUTRAL CONDUCTOR CLOSER TO CONNECTION 5.) POWER RELEASE SUBJECT TO FINAL INSPECTION APPROVAL OF BUILDING INSPECTOR AND ELECTRICAL INSPECTOR. NEED ALL UNITS UNLOCKED. |
12/01/2000 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | |
09/05/2001 | PLUMBING - FINAL | TRINIVJR | Approved | IVRS - Inspection 0000*1.) PLDG FINAL IS OK 2.) OK FOR C OF O. |
09/19/2001 | PERMIT FINALED | FIRE | Approved |