Permit: DP22-0261
Permit Details
Apply Date:
09/12/2022
Applicant:
Tracy Garrison
Description:
Site/Grading/Swppp - Parking Lot Reid Park and Reid Park Zoo. New parking lot for future Reid Park Z
Permit Reviews
Permit Number - DP22-0261
Permit Status: Complete
Permit Description: Site/Grading/Swppp - Parking Lot Reid Park and Reid Park Zoo. New parking lot for future Reid Park Z
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/12/2022 | DEV PKG - OK TO SUBMIT | 09/30/2022 | COMPLETED |
10/12/2022 | DEV PKG | 10/19/2022 | ACTIVE |
10/13/2022 | DEV PKG - OK TO SUBMIT | 10/19/2022 | COMPLETED |
02/15/2023 | DEVELOPMENT PACKAGE REVIEW v.2 | 03/28/2023 | APPROVED |
10/28/2022 | DEVELOPMENT PACKAGE REVIEW v.1 | 12/01/2022 | REQUIRES RESUBMIT |
Outstanding Inspections
Permit Status: Complete
Permit Number: DP22-0261
Permite Description: Site/Grading/Swppp - Parking Lot Reid Park and Reid Park Zoo. New parking lot for future Reid Park Z
Total Outstanding Inspections - 5
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/19/2024 | PDSD Site/Engineering Division - Landscaping | N/A | Partial Pass | 260’ of fence panel is being moved from SW corner of therapy pool building to SE corner of new pool building and relocated on NW side of parking lot. |
05/10/2023 | SITE - SWPPP Correction Notice | N/A | Complete (Recurring) | Contractors not on site I walked to perimeters of the project I have no concerns with swap at this time |
04/04/2023 | PDSD Engineering Division Pre-Construction SITE | N/A | Complete (Recurring) | Informed the contractor they needed to call if for inspections every two weeks regardless |
11/02/2023 | COT - ENGR - Stormwater | N/A | Complete (Recurring) | All setups and controls are in place, majority of curb and sidewalks are completed overall site is maintained and clean. |
12/18/2023 | SITE - Zoning Final | N/A | Partial Pass | Contractors working on the north part of the parking lot so I just gave them a continuation |
Completed Inspections
Permit Status: Complete
Permit Number: DP22-0261
Permit Description: Site/Grading/Swppp - Parking Lot Reid Park and Reid Park Zoo. New parking lot for future Reid Park Z
Total Completed Inspections - 16
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/20/2023 | COT - ENGR - Signage Final | Passed | ||
02/21/2024 | ENGR - Drainage Structures | Passed | ||
04/03/2024 | ENGR Engineering Final | Passed | This permit is ready for a TCO4 on the parking lot and driveline. Contractor will fence off the fire line curb down to the back side of the ZOO sign and across to the grass area to close off the next phase of construction, (the old parking lot). This will also allow for pedestrian access and vehicles to enter the new parking lot and have access to both buildings. Van accessible spaces to the right side of cross hatch areas are not right for van accessible access without forcing an accessible van to back into a space. The van accessible space on the south side of the pool bld. at the entrance is also forcing someone to back into the space. |
|
04/08/2024 | SITE - SWPPP Correction Notice | Passed | ||
04/09/2024 | SITE | Passed | Water harvesting has been observed and looks to be in conformance to plan. | |
04/08/2024 | Verify required native plant protection, relocation, removal is completed prior to activity on job site | Passed | NPPO on the south side of drive lane will be moved over to the new DP as it has a water line going through it for that DP permit. | |
04/08/2024 | SITE - Stormwater Follow-up | Passed | ||
04/08/2024 | ENGR Grading Final | Passed | On parking lot north side of pool and drive lane going around pool Bld. | |
04/08/2024 | SITE - Stormwater Setup and Controls | Passed | On parking lot and drive lane | |
04/08/2024 | City of Tucson (COT) Planning and Development Services Engineering (ENGR) Zoning Compliance Inspection | Passed | Passed on the new north parking lot | |
04/08/2024 | PDSD Engineering Division Pre-Construction SITE | Passed | Passed | |
05/29/2024 | COT - ENGR - Stormwater | Passed | ||
05/29/2024 | COT - FCON - Fire - Final | Passed | ||
05/29/2024 | Final inspection to ensure all landscape and water harvesting SITE | Passed | ||
05/29/2024 | SITE - Stormwater Final Inspection | Passed | ||
05/29/2024 | SITE - Zoning Final | Passed |