Permit Details

Status:
Complete
Type:
Development Package
Apply Date:
09/12/2022
Applicant:
Tracy Garrison
Description:
Site/Grading/Swppp - Parking Lot Reid Park and Reid Park Zoo. New parking lot for future Reid Park Z

Permit Reviews

Permit Number - DP22-0261
Permit Status: Complete
Permit Description: Site/Grading/Swppp - Parking Lot Reid Park and Reid Park Zoo. New parking lot for future Reid Park Z
Start Date Submittal Complete Date Status  
09/12/2022 DEV PKG - OK TO SUBMIT 09/30/2022 COMPLETED Review Details
10/12/2022 DEV PKG 10/19/2022 ACTIVE Review Details
10/13/2022 DEV PKG - OK TO SUBMIT 10/19/2022 COMPLETED Review Details
02/15/2023 DEVELOPMENT PACKAGE REVIEW v.2 03/28/2023 APPROVED Review Details
10/28/2022 DEVELOPMENT PACKAGE REVIEW v.1 12/01/2022 REQUIRES RESUBMIT Review Details

Outstanding Inspections

Permit Status: Complete
Permit Number: DP22-0261
Permite Description: Site/Grading/Swppp - Parking Lot Reid Park and Reid Park Zoo. New parking lot for future Reid Park Z
Total Outstanding Inspections - 5
Last Inspection Date Description Inspector Results Comments
01/19/2024 PDSD Site/Engineering Division - Landscaping N/A Partial Pass 260’ of fence panel is being moved from SW corner of therapy pool building to SE corner of new pool building and relocated on NW side of parking lot.
05/10/2023 SITE - SWPPP Correction Notice N/A Complete (Recurring) Contractors not on site I walked to perimeters of the project I have no concerns with swap at this time
04/04/2023 PDSD Engineering Division Pre-Construction SITE N/A Complete (Recurring) Informed the contractor they needed to call if for inspections every two weeks regardless
11/02/2023 COT - ENGR - Stormwater N/A Complete (Recurring) All setups and controls are in place, majority of curb and sidewalks are completed overall site is maintained and clean.
12/18/2023 SITE - Zoning Final N/A Partial Pass Contractors working on the north part of the parking lot so I just gave them a continuation

Completed Inspections

Permit Status: Complete
Permit Number: DP22-0261
Permit Description: Site/Grading/Swppp - Parking Lot Reid Park and Reid Park Zoo. New parking lot for future Reid Park Z
Total Completed Inspections - 16
Date Description Inspector Results Comments
12/20/2023 COT - ENGR - Signage Final Passed
02/21/2024 ENGR - Drainage Structures Passed
04/03/2024 ENGR Engineering Final Passed This permit is ready for a TCO4 on the parking lot and driveline.
Contractor will fence off the fire line curb down to the back side of the ZOO sign and across to the grass area to close off the next phase of construction, (the old parking lot). This will also allow for pedestrian access and vehicles to enter the new parking lot and have access to both buildings.

Van accessible spaces to the right side of cross hatch areas are not right for van accessible access without forcing an accessible van to back into a space.

The van accessible space on the south side of the pool bld. at the entrance is also forcing someone to back into the space.
04/08/2024 SITE - SWPPP Correction Notice Passed
04/09/2024 SITE Passed Water harvesting has been observed and looks to be in conformance to plan.
04/08/2024 Verify required native plant protection, relocation, removal is completed prior to activity on job site Passed NPPO on the south side of drive lane will be moved over to the new DP as it has a water line going through it for that DP permit.
04/08/2024 SITE - Stormwater Follow-up Passed
04/08/2024 ENGR Grading Final Passed On parking lot north side of pool and drive lane going around pool Bld.
04/08/2024 SITE - Stormwater Setup and Controls Passed On parking lot and drive lane
04/08/2024 City of Tucson (COT) Planning and Development Services Engineering (ENGR) Zoning Compliance Inspection Passed Passed on the new north parking lot
04/08/2024 PDSD Engineering Division Pre-Construction SITE Passed Passed
05/29/2024 COT - ENGR - Stormwater Passed
05/29/2024 COT - FCON - Fire - Final Passed
05/29/2024 Final inspection to ensure all landscape and water harvesting SITE Passed
05/29/2024 SITE - Stormwater Final Inspection Passed
05/29/2024 SITE - Zoning Final Passed