Permit: DP22-0216
Permit Details
Status:
Complete
Type:
Development Package
Address:
2850 W BLACK CLOUD CT
Address NEW:
2850 W BLACK CLOUD CT
Apply Date:
08/08/2022
Applicant:
Jeffrey Stanley
Description:
Grading - Las Nubes, Lot 10.
Permit Reviews
Permit Number - DP22-0216
Permit Status: Complete
Permit Description: Grading - Las Nubes, Lot 10.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/08/2022 | DEV PKG - OK TO SUBMIT (GRADING ONLY) | 08/18/2022 | COMPLETED |
| 08/18/2022 | DEV PKG - OK TO SUBMIT | 08/18/2022 | COMPLETED |
| 08/18/2022 | GRADING | 09/15/2022 | COMPLETED |
| 09/30/2022 | GRADING | 10/17/2022 | ACTIVE |
| 10/28/2022 | DEVELOPMENT PACKAGE REVIEW v.1 | 11/14/2022 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: DP22-0216
Permite Description: Grading - Las Nubes, Lot 10.
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/03/2023 | SITE - SWPPP Correction Notice | N/A | Not Applicable | |
| COT - FCON - Fire - Final | N/A | Not Ready | No access to job site. Gate Knox switch not active. |
Completed Inspections
Permit Status: Complete
Permit Number: DP22-0216
Permit Description: Grading - Las Nubes, Lot 10.
Total Completed Inspections - 16
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/03/2023 | COT - ENGR - Signage Final | Passed | ||
| 08/03/2023 | SITE - Zoning Final | Passed | ||
| 08/03/2023 | Final inspection to ensure all landscape and water harvesting SITE | Passed | ||
| 08/03/2023 | SITE - Stormwater Setup and Controls | Passed | stormwater set up and control inspection is to be requested at the beginning of the project. Stormwater controls are to remain in place throughout the project, and Stormwater follow up inspections shall be continuous throughout the project. | |
| 08/03/2023 | SITE - Stormwater Follow-up | Passed | ||
| 08/03/2023 | SITE | Passed | ||
| 08/03/2023 | City of Tucson (COT) Planning and Development Services Engineering (ENGR) Zoning Compliance Inspection | Passed | ||
| 08/03/2023 | COT - ENGR - Stormwater | Passed | ||
| 08/03/2023 | ENGR - Drainage Structures | Passed | ||
| 08/03/2023 | COT - ENGR - Site - Assurance Release | Passed | ||
| 08/03/2023 | ENGR Engineering Final | Passed | ||
| 08/03/2023 | SITE - Stormwater Final Inspection | Passed | ||
| 08/03/2023 | PDSD Engineering Division Pre-Construction SITE | Passed | Josh, please schedule preconstruction meeting at the start of each project rather than at the end of the project. Thank you. | |
| 08/03/2023 | PDSD Site/Engineering Division - Landscaping | Passed | ||
| 08/03/2023 | PDSD Site/Engineering Division - NPPO | Passed | ||
| 09/26/2023 | Verify required native plant protection, relocation, removal is completed prior to activity on job site | Passed |