Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Details
Status:
Issued
Type:
Development Package
Apply Date:
07/01/2022
Applicant:
Lisa Bowers
Description:
*Revision #1 (wall height) started 6/17/2024* Site/Grading/Swppp - Tucson Electric Power Company. New substation.
Permit Reviews
Permit Number - DP22-0178
Permit Status: Issued
Permit Description: *Revision #1 (wall height) started 6/17/2024* Site/Grading/Swppp - Tucson Electric Power Company. New substation.
| Start Date |
Submittal |
Complete Date |
Status |
|
| 07/01/2022 |
DEV PKG - OK TO SUBMIT |
07/13/2022 |
COMPLETED |
Review Details |
| 07/13/2022 |
DEV PKG |
08/26/2022 |
COMPLETED |
Review Details |
| 11/09/2022 |
DEVELOPMENT PACKAGE REVIEW v.1 |
12/06/2022 |
APPROVED |
Review Details |
| 06/17/2024 |
DEVELOPMENT PACKAGE REVIEW v.1 |
07/01/2024 |
APPROVED |
Review Details |
Documents
| File Name |
Document Type |
|
| 1_SWPPP - TEP DEMOSS PETRIE 230KV SUBSTATION_V1.PDF |
DOCUMENTS |
VIEW
|
| 2_ JE FULLER DRAINAGE COMMENT RESPONSE -1ST REVIEW 2022-10-20 - UPLOADED FILE TYPE PLANS 1_V1.PDF |
DOCUMENTS |
VIEW
|
| 2_CIVIL RESPONSE LETTER 2022-10-20 - UPLOADED FILE TYPE PLANS 1_V1.PDF |
DOCUMENTS |
VIEW
|
| 2_LANDSCAPE RESPONSE LETTER 2022-10-20 - UPLOADED FILE TYPE PLANS 1_V1.PDF |
DOCUMENTS |
VIEW
|
| PLANS_1_DRAINAGE REPORT-2022-06-10_V1.PDF |
DOCUMENTS |
VIEW
|
| PLANS_1_PLAN SET_V1.PDF |
DOCUMENTS |
VIEW
|
| 2_DRAINAGE REPORT -TEP DMP 230KV SUBSTATION - 2022-10-19 2022-10-20 - UPLOADED FILE TYPE PLANS 1_V1.PDF |
DOCUMENTS |
VIEW
|
| 2_PLAN SET - 230KV - 2022-10-19 - COMPLETE 2022-10-20 - UPLOADED FILE TYPE PLANS 1_V1.PDF |
DOCUMENTS |
VIEW
|
| 2_SWPPP - 2022-10-19 2022-10-20 - UPLOADED FILE TYPE PLANS 1_V1.PDF |
DOCUMENTS |
VIEW
|
| PLANS_1_GEOTECH REPORT_V1.PDF |
DOCUMENTS |
VIEW
|
| 1_GEOTECH REPORT.PDF |
PLANS UNDER REVIEW |
VIEW
|
| 1_DRAINAGE REPORT.PDF |
PLANS UNDER REVIEW |
VIEW
|
| 1_DEV PACKAGE APPLICATION - 230KV_SIGNED.PDF |
PLANS UNDER REVIEW |
VIEW
|
| 1_ONLINE PERMIT APPLICATION, RECVD 06.21.22.PDF |
PLANS UNDER REVIEW |
VIEW
|
| 1_PLAN SET.PDF |
PLANS UNDER REVIEW |
VIEW
|
| 1_SWPPP - TEP DEMOSS PETRIE 230KV SUBSTATION.PDF |
PLANS UNDER REVIEW |
VIEW
|