Permit: DP22-0160
Permit Details
Status:
Issued
Type:
Development Package
Address:
2501 N FLOWING WELLS RD
Address NEW:
2501 N FLOWING WELLS RD
Apply Date:
06/13/2022
Applicant:
Lisa Bowers
Description:
Restricted Access - *Revision #1 started 3/14/24 (updated wall height)* Site/Grading/Swppp - Tucson Electric Power, Demoss Petrie Substation 138kV.
Permit Reviews
Permit Number - DP22-0160
Permit Status: Issued
Permit Description: Restricted Access - *Revision #1 started 3/14/24 (updated wall height)* Site/Grading/Swppp - Tucson Electric Power, Demoss Petrie Substation 138kV.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/13/2022 | DEV PKG - OK TO SUBMIT | 06/24/2022 | COMPLETED |
| 06/24/2022 | DEV PKG | 09/14/2022 | COMPLETED |
| 03/14/2024 | DEVELOPMENT PACKAGE NEW v.1 | 05/06/2024 | APPROVED |
Outstanding Inspections
Permit Status: Issued
Permit Number: DP22-0160
Permite Description: Restricted Access - *Revision #1 started 3/14/24 (updated wall height)* Site/Grading/Swppp - Tucson Electric Power, Demoss Petrie Substation 138kV.
Total Outstanding Inspections - 11
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2022 | PDSD Site/Engineering Division - Landscaping | N/A | Not Ready | |
| 10/26/2022 | SITE - SWPPP Correction Notice | N/A | Not Ready | |
| 10/26/2022 | PDSD Site/Engineering Division - NPPO | N/A | Not Ready | |
| 10/27/2022 | ENGR Engineering Final | N/A | Not Ready | |
| 10/26/2022 | SITE - Stormwater Follow-up | N/A | Not Ready | |
| 10/27/2022 | ENGR Grading Final | N/A | Not Ready | |
| 10/26/2022 | SITE - SWPPP Violation Notice | N/A | Not Ready | |
| 10/26/2022 | SITE - Stormwater Final Inspection | N/A | Not Ready | |
| 10/26/2022 | SITE - Stormwater Setup and Controls | N/A | Not Ready | |
| 10/26/2022 | PDSD Engineering Division Pre-Construction SITE | N/A | Not Ready | |
| 10/27/2022 | COT - ENGR - Signage Final | N/A | Not Ready |