Permit: DP22-0114
Permit Details
Apply Date:
05/04/2022
Applicant:
Ted Herman
Description:
Site/Grading - Crossroads Festival PAD, new Chipotle restaurant.
Permit Reviews
Permit Number - DP22-0114
Permit Status: Complete
Permit Description: Site/Grading - Crossroads Festival PAD, new Chipotle restaurant.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/04/2022 | DEV PKG - OK TO SUBMIT | 05/12/2022 | COMPLETED |
05/12/2022 | DEV PKG | 07/28/2022 | COMPLETED |
08/22/2022 | DEV PKG - RESUBMITTAL | 09/28/2022 | COMPLETED |
10/05/2022 | DEV PKG - RESUBMITTAL | 10/19/2022 | COMPLETED |
01/06/2023 | DEVELOPMENT PACKAGE REVIEW v.1 | 02/03/2023 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: DP22-0114
Permite Description: Site/Grading - Crossroads Festival PAD, new Chipotle restaurant.
Total Outstanding Inspections - 2
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/18/2023 | Verify required native plant protection, relocation, removal is completed prior to activity on job site | N/A | Not Applicable | |
05/18/2023 | COT - FCON - Fire - Final | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: DP22-0114
Permit Description: Site/Grading - Crossroads Festival PAD, new Chipotle restaurant.
Total Completed Inspections - 9
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/18/2023 | SITE - Zoning Final | Passed | ||
05/17/2023 | SITE - Stormwater Final Inspection | Passed | ||
05/18/2023 | Final inspection to ensure all landscape and water harvesting SITE | Passed | ||
05/18/2023 | COT - ENGR - Stormwater | Passed | ||
05/18/2023 | PDSD Engineering Division Pre-Construction SITE | Passed | Project is complete at this time. Contractor advised to schedule preconstruction meetings prior to start of Project. | |
05/18/2023 | PDSD Site/Engineering Division - NPPO | Passed | ||
05/18/2023 | PDSD Site/Engineering Division - Landscaping | Passed | ||
05/18/2023 | ENGR Grading Final | Passed | ||
07/28/2023 | ENGR Engineering Final | Passed | per phone conversation approved by DRoberts |