Permit: DP22-0039
Permit Details
Apply Date:
02/25/2022
Applicant:
Cary Broschat
Description:
SITE: City of Tucson - Hayden Udall. Solar 650 kW AC Photovoltaic, ground-mount and floating arrays
Permit Reviews
Permit Number - DP22-0039
Permit Status: Complete
Permit Description: SITE: City of Tucson - Hayden Udall. Solar 650 kW AC Photovoltaic, ground-mount and floating arrays
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/25/2022 | DEV PKG - OK TO SUBMIT | 03/07/2022 | COMPLETED |
03/07/2022 | DEV PKG | 03/23/2022 | COMPLETED |
04/28/2022 | DEV PKG - RESUBMITTAL | 06/02/2022 | COMPLETED |
08/08/2022 | DEV PKG - RESUBMITTAL | 08/16/2022 | COMPLETED |
11/09/2022 | DEVELOPMENT PACKAGE REVIEW v.2 | 11/29/2022 | REQUIRES RESUBMIT |
01/05/2023 | DEVELOPMENT PACKAGE REVIEW v.1 | 01/05/2023 | APPROVED |
11/09/2022 | DEVELOPMENT PACKAGE REVIEW v.1 | 11/09/2022 | REQUIRES RESUBMIT |
11/29/2022 | DEVELOPMENT PACKAGE REVIEW v.3 | 01/05/2023 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: DP22-0039
Permite Description: SITE: City of Tucson - Hayden Udall. Solar 650 kW AC Photovoltaic, ground-mount and floating arrays
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/28/2022 | ENGR Grading Final | N/A | Canceled | {Activity date: 04/28/2022; Status: Not Applicable; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - NA} |
Completed Inspections
Permit Status: Complete
Permit Number: DP22-0039
Permit Description: SITE: City of Tucson - Hayden Udall. Solar 650 kW AC Photovoltaic, ground-mount and floating arrays
Total Completed Inspections - 7
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/21/2023 | Verify required native plant protection, relocation, removal is completed prior to activity on job site | Passed | ||
04/21/2023 | PDSD Engineering Division Pre-Construction SITE | Passed | ||
07/26/2023 | ENGR Engineering Final | Passed | ||
07/26/2023 | COT - ENGR - Stormwater | Passed | This is the final for the STORMWATER also | |
07/27/2023 | SITE - Stormwater Final Inspection | Passed | ||
07/31/2023 | Final inspection to ensure all landscape and water harvesting SITE | Passed | ||
07/31/2023 | SITE - Zoning Final | Passed |