Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: DP21-0299
Permit Details
Status:
Complete
Type:
Development Package
Address:
2960 N CAMPBELL AV
Address NEW:
2960 N CAMPBELL AV
Apply Date:
11/03/2021
Applicant:
Description:
Site/Grading - Doughbird/Flower Child Restaurant.
Permit Reviews
Permit Number - DP21-0299
Permit Status: Complete
Permit Description: Site/Grading - Doughbird/Flower Child Restaurant.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/23/2022 | DEV PKG - RESUBMITTAL | 04/07/2022 | COMPLETED |
| 09/26/2022 | DEV PKG - OK TO SUBMIT | 10/14/2022 | COMPLETED |
| 09/28/2022 | DEV PKG - REVISION | 10/14/2022 | ACTIVE |
| 11/03/2021 | DEV PKG - OK TO SUBMIT | 11/12/2021 | COMPLETED |
| 11/12/2021 | DEV PKG | 01/31/2022 | COMPLETED |
| 10/27/2022 | DEVELOPMENT PACKAGE REVIEW v.1 | 12/05/2022 | APPROVED |
| 02/02/2023 | DEVELOPMENT PACKAGE REVIEW v.1 | 04/07/2023 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: DP21-0299
Permite Description: Site/Grading - Doughbird/Flower Child Restaurant.
Total Outstanding Inspections - 14
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/16/2022 | SITE - Stormwater Setup and Controls | N/A | Complete (Recurring) | {Activity date: 06/16/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Provide concrete containment and other stormwater protections as required} |
| 06/16/2022 | PDSD Engineering Division Pre-Construction SITE | N/A | Complete (Recurring) | {Activity date: 06/16/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Unscheduled courtesy inspection for James with WE O’Neill at 268-3013. Project is underway. No inspection history as of this date. Please schedule inspections by weekly and as needed. Provide concrete containment and stormwater protection. Pay special attention to water harvesting areas and accessibility requirements. Stormwater to pass through sidewalk scuppers. Existing trash enclosure specified to remain.} |
| 10/04/2022 | SITE - Stormwater Follow-up | N/A | Complete (Recurring) | {Activity date: 10/04/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. All mud and track out is contained within parking lot } ; {Activity date: 08/10/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued. Standing water on site. Track out contained within private parking area but outside of temporary fencing.} ; {Activity date: 07/27/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. All materials contained within the site. Standing Water and mud conditions} ; {Activity date: 07/15/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued} ; {Activity date: 07/06/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. Track out contained within private parking area} ; {Activity date: 06/29/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued} |
| 10/26/2022 | SITE - SWPPP Correction Notice | N/A | Not Ready | |
| 10/27/2022 | ENGR Grading Final | N/A | Not Ready | |
| 10/26/2022 | SITE - SWPPP Violation Notice | N/A | Not Ready | |
| 10/27/2022 | COT - ENGR - Signage Final | N/A | Not Ready | |
| 03/02/2023 | COT - FCON - Fire - Final | N/A | Not Applicable | |
| 03/03/2023 | COT - ENGR - Stormwater | N/A | Not Ready | The contractor is still working on this project is not ready for this inspection to be either partially approved for fully approved. They will be working on raising the manhole covers to finish pavement grades. They will be working on installing the handicap access signs for the parking spaces, they will be working on General cleanup of the site and removal of us excess material before this inspection is rescheduled for a final CofOor rescheduled for a temporary Cof0 |
| 03/06/2023 | SITE - Zoning Final | N/A | Partial Pass | This may not be applicable, will verify with Zoning first |
| 03/03/2023 | PDSD Site/Engineering Division - Landscaping | N/A | Not Ready | The contractor is still working on this project is not ready for this inspection to be either partially approved for fully approved. They will be working on raising the manhole covers to finish pavement grades. They will be working on installing the handicap access signs for the parking spaces, they will be working on General cleanup of the site and removal of us excess material before this inspection is rescheduled for a final CofOor rescheduled for a temporary Cof0 |
| 03/03/2023 | Final inspection to ensure all landscape and water harvesting SITE | N/A | Not Ready | The contractor is still working on this project is not ready for this inspection to be either partially approved for fully approved. They will be working on raising the manhole covers to finish pavement grades. They will be working on installing the handicap access signs for the parking spaces, they will be working on General cleanup of the site and removal of us excess material before this inspection is rescheduled for a final CofOor rescheduled for a temporary Cof0 |
| 03/03/2023 | ENGR Engineering Final | N/A | Not Ready | The contractor is still working on this project is not ready for this inspection to be either partially approved for fully approved. They will be working on raising the manhole covers to finish pavement grades. They will be working on installing the handicap access signs for the parking spaces, they will be working on General cleanup of the site and removal of us excess material before this inspection is rescheduled for a final CofOor rescheduled for a temporary Cof0 |
| 03/06/2023 | SITE - Stormwater Final Inspection | N/A | Not Ready | The sun will need to be clean and clear prior to the final before this inspection can be approved |
Completed Inspections
Permit Status: Complete
Permit Number: DP21-0299
Permit Description: Site/Grading - Doughbird/Flower Child Restaurant.
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/22/2023 | COT - ENGR - Stormwater | Passed | ||
| 03/23/2023 | SITE - Zoning Final | Passed | ||
| 03/30/2023 | PDSD Site/Engineering Division - Landscaping | Passed | ||
| 03/30/2023 | Final inspection to ensure all landscape and water harvesting SITE | Passed | ||
| 03/30/2023 | ENGR Engineering Final | Passed | ||
| 03/30/2023 | SITE - Stormwater Final Inspection | Passed |