Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Inspections
Type:
Development Package
Address NEW:
351 N COMMERCE PARK LP
Apply Date:
05/24/2021
Applicant:
Description:
Revision 1 - Restricted Access SITE - Intermountain Academy Park Improvements. Shade structures over playground equipment. (owner

Permit Reviews

Permit Number - DP21-0129
Permit Status: Inspections
Permit Description: Revision 1 - Restricted Access SITE - Intermountain Academy Park Improvements. Shade structures over playground equipment. (owner
Start Date Submittal Complete Date Status  
05/24/2021 DEV PKG - OK TO SUBMIT 06/10/2021 COMPLETED Review Details
06/28/2021 DEV PKG - OK TO SUBMIT 07/01/2021 COMPLETED Review Details
07/01/2021 DEV PKG 08/05/2021 COMPLETED Review Details
10/12/2021 DEV PKG - RESUBMITTAL 11/08/2021 COMPLETED Review Details
12/21/2021 DEV PKG - RESUBMITTAL 01/10/2022 COMPLETED Review Details
07/30/2024 DEVELOPMENT PACKAGE NEW REVISION v.1 08/28/2024 APPROVED Review Details

Outstanding Inspections

Permit Status: Inspections
Permit Number: DP21-0129
Permite Description: Revision 1 - Restricted Access SITE - Intermountain Academy Park Improvements. Shade structures over playground equipment. (owner
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
05/08/2025 Assurance - Initial (Roadways, Utilities, Basins) ENGR N/A Not Ready 5/8/25 Jacob Thrasher 5206973201
Third party test results for completed work still needed.
Basin also has been proposed but not approved.

Completed Inspections

Permit Status: Inspections
Permit Number: DP21-0129
Permit Description: Revision 1 - Restricted Access SITE - Intermountain Academy Park Improvements. Shade structures over playground equipment. (owner
Total Completed Inspections - 2
Date Description Inspector Results Comments
07/27/2022 ENGR Engineering Final Passed {Activity date: 07/27/2022; Status: Approved; Inspector: BBENEDON; Comment: Entered by VVERA1 - Approved} ; {Activity date: 07/27/2022; Status: Approved; Inspector: BBENEDON; Comment: Entered by VVERA1 - Approved}
05/06/2025 PDSD Engineering Division Pre-Construction SITE Passed For the contractor to install all the track out rock and have all the testing done the subgrade day B grade asphalt and call him every two weeks for swap inspection