Permit: DP21-0127
Permit Details
Apply Date:
05/24/2021
Applicant:
Description:
Site/Grading/Floodplain - Tucson Rolling Shutters, new building addition.
Permit Reviews
Permit Number - DP21-0127
Permit Status: Complete
Permit Description: Site/Grading/Floodplain - Tucson Rolling Shutters, new building addition.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/24/2021 | DEV PKG - OK TO SUBMIT | 05/28/2021 | COMPLETED |
| 06/24/2021 | DEV PKG - OK TO SUBMIT | 06/30/2021 | COMPLETED |
| 06/30/2021 | DEV PKG | 08/30/2021 | COMPLETED |
| 09/10/2021 | DEV PKG - RESUBMITTAL | 12/03/2021 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP21-0127
Permit Description: Site/Grading/Floodplain - Tucson Rolling Shutters, new building addition.
Total Completed Inspections - 9
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/10/2022 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 06/10/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by VVERA1 - IS APPROVED} | |
| 06/13/2022 | SITE - SWPPP Correction Notice | Passed | {Activity date: 06/13/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
| 06/13/2022 | SITE - Stormwater Follow-up | Passed | {Activity date: 06/13/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 06/08/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - CN /WORKING ON INSTALLING PLANTS IN THE BASIN.} ; {Activity date: 05/12/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by RSALDAT1 - CN /NO CONCERNS AS OF TODAY} ; {Activity date: 03/30/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - CN /CLEAN UP THE BASIN} ; {Activity date: 02/17/2022; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - NO CONCERNS AT THIS TIME, ALL STORMWATER ITEMS HAVE BEEN ADDRESSED AND MAINTAINED. THE RAIN FOR THIS WEEK HAS BEEN LESS THAT 0.1INCHES BUT HAS BEEN NOTED IN THE LOGS.} ; {Activity date: 02/07/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - CN} ; {Activity date: 01/27/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - CN GOOD AS OF TODAY.} | |
| 06/13/2022 | ENGR Grading Final | Passed | {Activity date: 06/13/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
| 06/13/2022 | SITE - SWPPP Violation Notice | Passed | {Activity date: 06/13/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
| 06/13/2022 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 06/13/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 01/04/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - CN / INSTALLED TRACK OUT ROCK AND WATTLES. GOOD AS OF TODAY.} | |
| 06/13/2022 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 06/13/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 12/15/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - CN /INFORMED THE CONTRACTOR TO CALL IN THE INSPECTION EVERY TWO WEEKS . INSTALL THE WATTLES AND TRACK OUT ROCK.} | |
| 06/16/2022 | ENGR Engineering Final | Passed | {Activity date: 06/16/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by NGARCIA3 - APPROVED} | |
| 06/16/2022 | SITE - Stormwater Final Inspection | Passed | {Activity date: 06/16/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by NGARCIA3 - APPROVED} |