Permit: DP21-0126
Permit Details
Apply Date:
05/20/2021
Applicant:
Description:
SITE - Raising Canes. Drive-thru canopy.
Permit Reviews
Permit Number - DP21-0126
Permit Status: Complete
Permit Description: SITE - Raising Canes. Drive-thru canopy.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/20/2021 | DEV PKG - OK TO SUBMIT | 05/26/2021 | COMPLETED |
| 05/26/2021 | DEV PKG | 06/22/2021 | COMPLETED |
| 08/19/2021 | DEV PKG - RESUBMITTAL | 08/25/2021 | COMPLETED |
| 12/14/2022 | DEVELOPMENT PACKAGE REVIEW v.1 | 01/09/2023 | APPROVED |
| 12/14/2022 | DEVELOPMENT PACKAGE REVIEW v.1 | 12/22/2022 | REQUIRES RESUBMIT |
Outstanding Inspections
Permit Status: Complete
Permit Number: DP21-0126
Permite Description: SITE - Raising Canes. Drive-thru canopy.
Total Outstanding Inspections - 9
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2022 | PDSD Site/Engineering Division - Landscaping | N/A | Not Ready | |
| 10/26/2022 | SITE - SWPPP Correction Notice | N/A | Not Ready | |
| 10/26/2022 | PDSD Site/Engineering Division - NPPO | N/A | Not Ready | |
| 10/26/2022 | SITE - Stormwater Follow-up | N/A | Not Ready | |
| 10/27/2022 | ENGR Grading Final | N/A | Not Ready | |
| 10/26/2022 | SITE - SWPPP Violation Notice | N/A | Not Ready | |
| 10/26/2022 | SITE - Stormwater Setup and Controls | N/A | Not Ready | |
| 10/26/2022 | PDSD Engineering Division Pre-Construction SITE | N/A | Not Ready | |
| 02/22/2023 | ENGR - Drainage Structures | N/A | Partial Pass | Preview board footing OK. Gabe 623-910-4714 n/a per bbenedon |
Completed Inspections
Permit Status: Complete
Permit Number: DP21-0126
Permit Description: SITE - Raising Canes. Drive-thru canopy.
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/23/2023 | COT - ENGR - Signage Final | Passed | ||
| 03/23/2023 | SITE - Stormwater Final Inspection | Passed | Joy | |
| 03/23/2023 | ENGR Engineering Final | Passed |