Permit: DP21-0050
Permit Details
Apply Date:
02/18/2021
Applicant:
Fernando Camacho
Description:
Site/Grading - Carniceria Camacho Addition.
Permit Reviews
Permit Number - DP21-0050
Permit Status: Issued
Permit Description: Site/Grading - Carniceria Camacho Addition.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/18/2021 | DEV PKG - OK TO SUBMIT | 02/22/2021 | COMPLETED |
| 02/22/2021 | DEV PKG | 03/31/2021 | COMPLETED |
| 05/17/2021 | DEV PKG - RESUBMITTAL | 07/01/2021 | COMPLETED |
| 08/09/2021 | DEV PKG - RESUBMITTAL | 09/16/2021 | COMPLETED |
| 09/16/2021 | DEV PKG - RESUBMITTAL | 10/07/2021 | COMPLETED |
Outstanding Inspections
Permit Status: Issued
Permit Number: DP21-0050
Permite Description: Site/Grading - Carniceria Camacho Addition.
Total Outstanding Inspections - 11
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/13/2022 | SITE - Stormwater Follow-up | N/A | Complete (Recurring) | {Activity date: 04/13/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - COMPLETED} |
| 10/27/2022 | PDSD Site/Engineering Division - Landscaping | N/A | Not Ready | |
| 10/26/2022 | SITE - SWPPP Correction Notice | N/A | Not Ready | |
| 10/26/2022 | PDSD Site/Engineering Division - NPPO | N/A | Not Ready | |
| 10/27/2022 | ENGR Engineering Final | N/A | Not Ready | |
| 10/27/2022 | ENGR Grading Final | N/A | Not Ready | |
| 10/26/2022 | SITE - SWPPP Violation Notice | N/A | Not Ready | |
| 10/26/2022 | SITE - Stormwater Final Inspection | N/A | Not Ready | |
| 10/26/2022 | SITE - Stormwater Setup and Controls | N/A | Not Ready | |
| 10/27/2022 | COT - ENGR - Signage Final | N/A | Not Ready | |
| 02/16/2024 | PDSD Engineering Division Pre-Construction SITE | N/A | Canceled | Contacted the contractor for the site. They are not the contractor for this site and are asking to have their name removed. Inspection has been canceled. |