Grading - Barrio Ochoa, Lots 1 thru 5, and common area A (Retention Basin).
Permit Reviews
Permit Number - DP21-0016
Permit Status: Complete
Permit Description: Grading - Barrio Ochoa, Lots 1 thru 5, and common area A (Retention Basin).
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/19/2021 | DEV PKG - OK TO SUBMIT | 01/22/2021 | COMPLETED |
01/21/2021 | GRADING | 02/24/2021 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP21-0016
Permit Description: Grading - Barrio Ochoa, Lots 1 thru 5, and common area A (Retention Basin).
Total Completed Inspections - 2
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/14/2021 | ENGR Grading Final | Passed | {Activity date: 10/14/2021; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
06/07/2022 | ENGR Engineering Final | Passed | {Activity date: 06/07/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 10/14/2021; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - PHOTOS PROVIDED FOR THIS APPROVAL FROM 09/30/2019} ; {Activity date: 10/19/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - CN / THE DRAINAGE ISSUE HAD NOT BEEN ADDRESSED.THE ISSUE IS WEST OF THE HEADWALL THAT THE EROSION IS NEXT THE THE HEADWALL ON THE WEST SIDE .} ; {Activity date: 09/02/2021; Status: Continued; Inspector: MHERENANDEZ; Comment: Entered by NGARCIA3 - CN/ PLACING RIP RAP} ; {Activity date: 08/30/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - CN / CONTINUE TO GRADED AND PLACING RIP RAP} |