Permit: DP20-0263
Permit Details
Status:
Issued
Type:
Development Package
Address:
3606 W EAGLES VIEW PL
Address NEW:
3606 W EAGLES VIEW PL
Apply Date:
12/24/2020
Applicant:
Description:
GRADING - Stern Hays, new single-family residence.
Permit Reviews
Permit Number - DP20-0263
Permit Status: Issued
Permit Description: GRADING - Stern Hays, new single-family residence.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/11/2021 | DEV PKG - OK TO SUBMIT | 01/15/2021 | COMPLETED |
| 01/15/2021 | GRADING | 02/22/2021 | COMPLETED |
| 12/24/2020 | DEV PKG - OK TO SUBMIT | 01/05/2021 | COMPLETED |
Outstanding Inspections
Permit Status: Issued
Permit Number: DP20-0263
Permite Description: GRADING - Stern Hays, new single-family residence.
Total Outstanding Inspections - 9
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/30/2021 | SITE - Stormwater Follow-up | N/A | Complete (Recurring) | {Activity date: 08/30/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - CN} ; {Activity date: 08/09/2021; Status: Continued; Inspector: DROBERTS; Comment: Entered by NGARCIA3 - S PLAYERS CLUB- STORMWATER FOLLOWUP IS CONTINUED, NO CONCERNS ATTHIS TIME, NO WORK HAS STARTED AT THIS TIME CONTRACTOR IS WORKING ON NPPO ITEMS} ; {Activity date: 08/09/2021; Status: Continued; Inspector: DROBERTS; Comment: Entered by NGARCIA3 - STORMWATER FOLLOWUP IS CONTINUED, NO CONCERNS ATTHIS TIME, NO WORK HAS STARTED AT THIS TIME CONTRACTOR IS WORKING ON NPPO ITEMS} |
| 08/30/2021 | PDSD Engineering Division Pre-Construction SITE | N/A | Complete (Recurring) | {Activity date: 08/30/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - CN} ; {Activity date: 08/05/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by RSALDAT1 - CN/ MET WITH JIM VAVRA AND DAVID ROBERTS .THE CONVERSATION WAS ABOUT THE NPPO AND TO CALL IN EVERY TWO FOR INSPECTION.} |
| 10/27/2022 | PDSD Site/Engineering Division - Landscaping | N/A | Not Ready | |
| 10/26/2022 | PDSD Site/Engineering Division - NPPO | N/A | Not Ready | |
| 10/27/2022 | ENGR Engineering Final | N/A | Not Ready | |
| 10/27/2022 | ENGR Grading Final | N/A | Not Ready | |
| 10/26/2022 | SITE - Stormwater Final Inspection | N/A | Not Ready | |
| 10/26/2022 | SITE - Stormwater Setup and Controls | N/A | Not Ready | |
| 10/27/2022 | COT - ENGR - Signage Final | N/A | Not Ready |