Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: DP20-0169
Permit Details
Apply Date:
08/26/2020
Applicant:
Lisa Bowers
Description:
SITE- 1301 S. Stocker Drive, Emissions Facility, vehicular use area.
Permit Reviews
Permit Number - DP20-0169
Permit Status: Issued
Permit Description: SITE- 1301 S. Stocker Drive, Emissions Facility, vehicular use area.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/28/2020 | DEV PKG - OK TO SUBMIT | 08/27/2020 | COMPLETED |
08/05/2021 | DEV PKG - OK TO SUBMIT | 08/31/2021 | COMPLETED |
08/27/2020 | DEV PKG | 10/22/2020 | COMPLETED |
08/31/2021 | REVISION - - 1ST | 09/14/2021 | COMPLETED |
11/13/2020 | DEV PKG - RESUBMITTAL | 01/21/2021 | COMPLETED |
Outstanding Inspections
Permit Status: Issued
Permit Number: DP20-0169
Permite Description: SITE- 1301 S. Stocker Drive, Emissions Facility, vehicular use area.
Total Outstanding Inspections - 3
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/20/2021 | PDSD Site/Engineering Division - Landscaping | N/A | Complete (Recurring) | {Activity date: 05/20/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VLEON1 - CONTINUE PLACING RIP RAP} |
10/27/2022 | ENGR Grading Final | N/A | Not Ready | |
10/26/2022 | PDSD Engineering Division Pre-Construction SITE | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: DP20-0169
Permit Description: SITE- 1301 S. Stocker Drive, Emissions Facility, vehicular use area.
Total Completed Inspections - 8
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/29/2021 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 06/29/2021; Status: Approved; Inspector: MHERNANDEZ; Comment: Entered by RSALDAT1 - APPROVED} | |
06/29/2021 | COT - ENGR - Signage Final | Passed | {Activity date: 06/29/2021; Status: Approved; Inspector: MHERNANDEZ; Comment: Entered by RSALDAT1 - APPROVED} | |
10/31/2023 | ENGR Engineering Final | Passed | This project past six months ago | |
10/31/2023 | SITE - Stormwater Follow-up | Passed | I Projects past six months ago | |
10/31/2023 | ENGR Grading Final | Passed | This project was past six months ago | |
10/31/2023 | SITE - Stormwater Final Inspection | Passed | The project is past six months ago | |
10/31/2023 | SITE - Stormwater Setup and Controls | Passed | This project is past six months ago | |
10/31/2023 | PDSD Engineering Division Pre-Construction SITE | Passed | This project was past six months ago |