Permit: DP20-0158
Permit Details
Apply Date:
08/05/2020
Applicant:
David Gary Gerovac
Description:
SITE/GRADING - River Bend Apartments, new multi-family residential.
Permit Reviews
Permit Number - DP20-0158
Permit Status: Complete
Permit Description: SITE/GRADING - River Bend Apartments, new multi-family residential.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/06/2021 | DEV PKG - RESUBMITTAL | 01/06/2021 | COMPLETED |
| 02/04/2021 | DEV PKG - OK TO SUBMIT | 02/11/2021 | COMPLETED |
| 02/11/2021 | REVISION - - 1ST | 02/19/2021 | COMPLETED |
| 04/05/2021 | DEV PKG - OK TO SUBMIT | 04/16/2021 | COMPLETED |
| 04/16/2021 | REVISION - - 2ND | 04/29/2021 | ACTIVE |
| 07/07/2020 | DEV PKG - OK TO SUBMIT | 08/12/2020 | COMPLETED |
| 08/11/2020 | DEV PKG | 09/24/2020 | COMPLETED |
| 11/03/2020 | DEV PKG - RESUBMITTAL | 12/09/2020 | COMPLETED |
Outstanding Inspections
Permit Status: Complete
Permit Number: DP20-0158
Permite Description: SITE/GRADING - River Bend Apartments, new multi-family residential.
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/24/2022 | PDSD Site/Engineering Division - NPPO | N/A | Canceled | {Activity date: 01/24/2022; Status: Not Applicable; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - NA} |
| 01/24/2022 | COT - ENGR - Signage Final | N/A | Canceled | {Activity date: 01/24/2022; Status: Not Applicable; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - NA} |
Completed Inspections
Permit Status: Complete
Permit Number: DP20-0158
Permit Description: SITE/GRADING - River Bend Apartments, new multi-family residential.
Total Completed Inspections - 7
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/11/2021 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 02/11/2021; Status: Approved; Inspector: BBENEDON; Comment: Entered by VLEON1 - Approved. Jack with Canyon at 272-0748. Magnum contracting for site work. Cypress engineering. .72 acre. Provide inspection of stormwater controls. Project to get started next week. Located at the end of prince at the River. Riverbend Apartments.} | |
| 05/25/2021 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 05/25/2021; Status: Approved; Inspector: BBENEDON; Comment: Entered by VLEON1 - Approved. Jack with Canyon. Magnum contractors. No SWPPP required} ; {Activity date: 02/17/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Track out protection has been installed } |
|
| 01/24/2022 | SITE - Stormwater Follow-up | Passed | {Activity date: 01/24/2022; Status: Approved; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - APPROVED} ; {Activity date: 12/23/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. Track out and material stock piles on Prince Road due to main water line utilities} ; {Activity date: 12/15/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Utility work on Prince Road} ; {Activity date: 07/08/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continue. No issues this last storm event} ; {Activity date: 05/27/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VLEON1 - Continued. Minor track out noted.} ; {Activity date: 03/10/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VLEON1 - CONTINUE TRACK OUT NOTED ON PRINCE RD} ; {Activity date: 02/17/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Minor track out noted. Protections installed} | |
| 02/10/2022 | SITE - Stormwater Final Inspection | Passed | {Activity date: 02/10/2022; Status: Approved; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Approved} | |
| 02/23/2022 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 02/23/2022; Status: Approved; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Approved.Rick w canyon4051393 Please change permit status to final approval.} ; {Activity date: 01/25/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Landscaping in progress.} ; {Activity date: 01/24/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - CN} |
|
| 02/23/2022 | ENGR Engineering Final | Passed | {Activity date: 02/23/2022; Status: Approved; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Approved.Rick w canyon4051393 Please change permit status to final approval.} |
|
| 02/23/2022 | ENGR Grading Final | Passed | {Activity date: 02/23/2022; Status: Approved; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Approved.Rick w canyon4051393 Please change permit status to final approval.} ; {Activity date: 01/25/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Landscaping in progress.} ; {Activity date: 01/24/2022; Status: Approved; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - APPROVED} ; {Activity date: 01/11/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Drainage swale at rear} ; {Activity date: 12/22/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued. On going utility work within the right of way.} ; {Activity date: 12/14/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - . Continued. Utility work within the right of way in progress.} ; {Activity date: 11/30/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Main waterline work in progress. Jack With Canyon } ; {Activity date: 11/23/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Utility work in progress } ; {Activity date: 11/17/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Utility work in right of way. Fire mainline on site. Jack With Canyon} ; {Activity date: 11/04/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. utility work in progress. Work within the right of way. Lane closures in place. Chuck with Magnum contractors.} ; {Activity date: 10/20/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Utility work and building progress } ; {Activity date: 09/24/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Utility work in progress} ; {Activity date: 09/02/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - ontinued. Rough grading } ; {Activity date: 08/31/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. No activity on site after rain event} ; {Activity date: 08/17/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. No activity on site after last rain activity. Side is muddy. No issues offsite} ; {Activity date: 08/10/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continue. No activity at the rain event} ; {Activity date: 07/21/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Trash enclosure gates require a latching mechanism for both close and open positions. Consult designer for specifics. } ; {Activity date: 06/23/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VLEON1 - Continued. Street closure barricades in place. Building construction in progress} ; {Activity date: 05/27/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VLEON1 - Continued. No site work activity at this time. Material stock piles on site. Building construction in progress} ; {Activity date: 04/28/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Final grading. Jack with Canyon} ; {Activity date: 04/23/2021; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by VLEON1 - Partially approved. Parking lot drainage structure} ; {Activity date: 04/15/2021; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by VLEON1 - PARTIAL APPROVAL DRAINAGE STRUCTURE INSIDE PROPERTY PERIMETERS} ; {Activity date: 04/13/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Rough grading} ; {Activity date: 04/08/2021; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by VLEON1 - PARTIAL APPROVAL ROUGH GRADING, JACK WITH CANYON} |