Permit: DP20-0151
Permit Details
Status:
Complete
Type:
Development Package
Address:
4200 S HARRISON RD
Address NEW:
4200 S HARRISON RD
Apply Date:
07/24/2020
Applicant:
James McMurtrie
Description:
SITE/GRADING/SWPPP - Harrison Road inert materials landfill.
Permit Reviews
Permit Number - DP20-0151
Permit Status: Complete
Permit Description: SITE/GRADING/SWPPP - Harrison Road inert materials landfill.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/25/2020 | DEV PKG - OK TO SUBMIT | 07/29/2020 | COMPLETED |
| 07/29/2020 | DEV PKG | 09/01/2020 | COMPLETED |
| 10/09/2020 | DEV PKG - RESUBMITTAL | 12/02/2020 | COMPLETED |
| 12/17/2021 | DEV PKG - OK TO SUBMIT | 12/27/2021 | COMPLETED |
| 12/27/2021 | REVISION - - 1ST | 03/07/2022 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP20-0151
Permit Description: SITE/GRADING/SWPPP - Harrison Road inert materials landfill.
Total Completed Inspections - 9
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/14/2021 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 01/14/2021; Status: Approved; Inspector: DROBERTS; Comment: Entered by VLEON1 - APPROVED} | |
| 04/26/2022 | SITE - Stormwater Follow-up | Passed | {Activity date: 04/26/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by NGARCIA3 - APPROVED} ; {Activity date: 04/18/2022; Status: Continued; Inspector: DROBERTS; Comment: Entered by RSALDAT1 - CONTINUED SITE WORK NIT COMPLETE AT THIS TIME} ; {Activity date: 09/21/2021; Status: Continued; Inspector: DROBERTS; Comment: Entered by RSALDAT1 - CONTINUED, NO CONCERNS AT THIS TIME.} ; {Activity date: 04/29/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VLEON1 - } | |
| 05/23/2022 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 05/23/2022; Status: Approved; Inspector: DROBERT5; Comment: Entered by DROBERT5 - } | |
| 05/23/2022 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 05/23/2022; Status: Approved; Inspector: DROBERT5; Comment: Entered by DROBERT5 - } | |
| 05/23/2022 | ENGR Engineering Final | Passed | {Activity date: 05/23/2022; Status: Approved; Inspector: DROBERT5; Comment: Entered by DROBERT5 - } ; {Activity date: 03/24/2022; Status: Partial Approval; Inspector: MHERNANEZ; Comment: Entered by VVERA1 - PARTIAL DAVID ROBERTS WILL GAVE THE T C O. } ; {Activity date: 03/21/2022; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by NGARCIA3 - PARTIALLY APPROVED, OK FOR TCO FOR OCCUPANCY} ; {Activity date: 03/17/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - CN NEED TO RAISE THE HANDICAP RAMP PARKING SIGN TO 7’ AT THE BOTTOM OF THE SIGN.AND GRADE THE FRONT OF THE FRONT OF THE PARKING LOT . } |
|
| 05/23/2022 | ENGR Grading Final | Passed | {Activity date: 05/23/2022; Status: Approved; Inspector: DROBERT5; Comment: Entered by DROBERT5 - } | |
| 05/23/2022 | SITE - Stormwater Final Inspection | Passed | {Activity date: 05/23/2022; Status: Approved; Inspector: DROBERT5; Comment: Entered by DROBERT5 - } | |
| 05/23/2022 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 05/23/2022; Status: Approved; Inspector: DROBERT5; Comment: Entered by DROBERT5 - } | |
| 05/23/2022 | COT - ENGR - Signage Final | Passed | {Activity date: 05/23/2022; Status: Approved; Inspector: DROBERT5; Comment: Entered by DROBERT5 - } |