Permit Details

Status:
Complete
Type:
Development Package
Address:
1050 E 19TH ST
Address NEW:
1050 E 19TH ST
Apply Date:
07/08/2020
Applicant:
Kelly Rehm
Description:
Site - Technicians for Sustainability, commercial solar PV system, roof-mounted.

Permit Reviews

Permit Number - DP20-0139
Permit Status: Complete
Permit Description: Site - Technicians for Sustainability, commercial solar PV system, roof-mounted.
Start Date Submittal Complete Date Status  
06/09/2020 DEV PKG - OK TO SUBMIT 07/09/2020 COMPLETED Review Details
07/09/2020 DEV PKG 07/09/2020 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP20-0139
Permit Description: Site - Technicians for Sustainability, commercial solar PV system, roof-mounted.
Total Completed Inspections - 9
Date Description Inspector Results Comments
08/02/2022 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 08/02/2022; Status: Approved; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - APPROVED}
08/02/2022 PDSD Site/Engineering Division - NPPO Passed {Activity date: 08/02/2022; Status: Approved; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - APPROVED}
08/02/2022 ENGR Engineering Final Passed {Activity date: 08/02/2022; Status: Approved; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - APPROVED}
08/02/2022 SITE - Stormwater Follow-up Passed {Activity date: 08/02/2022; Status: Approved; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - APPROVED}
08/02/2022 ENGR Grading Final Passed {Activity date: 08/02/2022; Status: Approved; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - APPROVED 9190}
08/02/2022 SITE - Stormwater Final Inspection Passed {Activity date: 08/02/2022; Status: Approved; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - APPROVED}
08/02/2022 SITE - Stormwater Setup and Controls Passed {Activity date: 08/02/2022; Status: Approved; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - APPROVED}
08/02/2022 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 08/02/2022; Status: Approved; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - APPROVED}
08/02/2022 COT - ENGR - Signage Final Passed {Activity date: 08/02/2022; Status: Approved; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - APPROVED}