Permit: DP20-0031
Permit Details
Apply Date:
01/31/2020
Applicant:
Description:
SITE - Casa Maria Apartments, electric gate.
Permit Reviews
Permit Number - DP20-0031
Permit Status: Complete
Permit Description: SITE - Casa Maria Apartments, electric gate.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/04/2020 | DEV PKG | 03/05/2020 | COMPLETED |
03/16/2020 | DEV PKG - RESUBMITTAL | 04/16/2020 | COMPLETED |
12/30/2019 | DEV PKG - OK TO SUBMIT | 02/04/2020 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP20-0031
Permit Description: SITE - Casa Maria Apartments, electric gate.
Total Completed Inspections - 9
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/31/2020 | SITE - Stormwater Follow-up | Passed | {Activity date: 08/31/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Approved.} | |
08/31/2020 | SITE - Stormwater Final Inspection | Passed | {Activity date: 08/31/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Approved.} | |
08/31/2020 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 08/31/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Approved.} | |
09/01/2020 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 09/01/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Approved} | |
09/01/2020 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 09/01/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Approved} | |
09/18/2020 | ENGR Engineering Final | Passed | {Activity date: 09/18/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Approved} ; {Activity date: 09/09/2020; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - not ready. Fire has not approved permit T 20 CM02708} ; {Activity date: 09/01/2020; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Not ready. 24 foot clearance shown on plan, fire department access lockbox and accessible parking space and ramp shown on plan. Please provide the required items and/or revise the plan as necessary. Anne At 906-0219} | |
03/03/2022 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 03/03/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 07/23/2020; Status: Not Applicable; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Not applicable} | |
03/03/2022 | ENGR Grading Final | Passed | {Activity date: 03/03/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 05/27/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VLEON1 - Continued. Please change status to final approved, as all inspections have been approved} ; {Activity date: 09/01/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Approved} ; {Activity date: 08/31/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Approved} ; {Activity date: 07/01/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Continue. Gate and perimeter fencing has been installed by Dusty at 808-7682. Development package plan indicates additional work. Please schedule for all inspections when ready} | |
03/03/2022 | COT - ENGR - Signage Final | Passed | {Activity date: 03/03/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 07/23/2020; Status: Not Applicable; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Not applicable} |