Permit Details

Status:
Complete
Type:
Development Package
Address NEW:
3950 E IRVINGTON RD
Apply Date:
01/07/2020
Applicant:
Description:
SITE/GRADING/SWPPP - TEP, Phase 2, Irvington Facilities, operations center and office.

Permit Reviews

Permit Number - DP20-0006
Permit Status: Complete
Permit Description: SITE/GRADING/SWPPP - TEP, Phase 2, Irvington Facilities, operations center and office.
Start Date Submittal Complete Date Status  
01/09/2020 DEV PKG 02/12/2020 COMPLETED Review Details
02/28/2020 DEV PKG - RESUBMITTAL 03/13/2020 COMPLETED Review Details
05/17/2021 DEV PKG - OK TO SUBMIT 05/21/2021 COMPLETED Review Details
05/21/2021 REVISION - - 1ST 06/08/2021 COMPLETED Review Details
12/06/2019 DEV PKG - OK TO SUBMIT 01/09/2020 COMPLETED Review Details
01/09/2024 AS-BUILT v.1 01/17/2024 APPROVED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP20-0006
Permit Description: SITE/GRADING/SWPPP - TEP, Phase 2, Irvington Facilities, operations center and office.
Total Completed Inspections - 9
Date Description Inspector Results Comments
04/17/2020 SITE - Stormwater Setup and Controls Passed {Activity date: 04/17/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - Walk site with GC and third-party Via FaceTime.}
04/28/2021 SITE - Stormwater Follow-up Passed {Activity date: 04/28/2021; Status: Approved; Inspector: MHERNANDEZ; Comment: Entered by VLEON1 - } ; {Activity date: 11/10/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by PAHUMAD1 - Continue. No concerns at this time.} ; {Activity date: 10/29/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - Continue. No concerns at this time.} ; {Activity date: 10/21/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - Continue. No concerns at this time.} ; {Activity date: 09/30/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - Continue. No concerns at this time.} ; {Activity date: 09/11/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by JSCHNEI2 - Continue. No concerns at this time.} ; {Activity date: 09/09/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by JSCHNEI2 - Continue. No concerns at this time.} ; {Activity date: 08/04/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - Continue. No concerns at this time.} ; {Activity date: 07/13/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by JSCHNEI2 - Continue. No concerns at this time.}
12/03/2021 PDSD Site/Engineering Division - NPPO Passed {Activity date: 12/03/2021; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - SITE WORK IS STILL BEING COMPLETED AT THIS TIME. SITE OK FOR TCO FOR STOCKING PURPOSES ONLY. I HAVE ASKED THE CONTRACTOR TO RESCHEDULE AN INSPECTION FOR THE A TIME WHEN ALL OF THE CURRENT WORK AROUND THE FRONT ENTRY WAY IS COMPLETE IF THEY WOULD WANT A TCO FOR CUSTOMERS.}
12/03/2021 ENGR Grading Final Passed {Activity date: 12/03/2021; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - SITE WORK IS STILL BEING COMPLETED AT THIS TIME. SITE OK FOR TCO FOR STOCKING PURPOSES ONLY. I HAVE ASKED THE CONTRACTOR TO RESCHEDULE AN INSPECTION FOR THE A TIME WHEN ALL OF THE CURRENT WORK AROUND THE FRONT ENTRY WAY IS COMPLETE IF THEY WOULD WANT A TCO FOR CUSTOMERS.}
12/03/2021 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 12/03/2021; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - SITE WORK IS STILL BEING COMPLETED AT THIS TIME. SITE OK FOR TCO FOR STOCKING PURPOSES ONLY. I HAVE ASKED THE CONTRACTOR TO RESCHEDULE AN INSPECTION FOR THE A TIME WHEN ALL OF THE CURRENT WORK AROUND THE FRONT ENTRY WAY IS COMPLETE IF THEY WOULD WANT A TCO FOR CUSTOMERS.} ; {Activity date: 05/25/2021; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - OH PARKING OK FOR A TCO}
12/03/2021 COT - ENGR - Signage Final Passed {Activity date: 12/03/2021; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - SITE WORK IS STILL BEING COMPLETED AT THIS TIME. SITE OK FOR TCO FOR STOCKING PURPOSES ONLY. I HAVE ASKED THE CONTRACTOR TO RESCHEDULE AN INSPECTION FOR THE A TIME WHEN ALL OF THE CURRENT WORK AROUND THE FRONT ENTRY WAY IS COMPLETE IF THEY WOULD WANT A TCO FOR CUSTOMERS.}
06/26/2023 SITE - Stormwater Final Inspection Passed
06/26/2023 ENGR Engineering Final Passed
06/26/2023 PDSD Site/Engineering Division - Landscaping Passed