Permit: DP19-0190
Permit Details
Status:
Approved
Type:
Development Package
Address:
311 E CONGRESS ST
Address NEW:
311 E CONGRESS ST
Apply Date:
08/08/2019
Applicant:
Lisa Bowers
Description:
SITE/GRADING - Hotel Congress, stage, storage bldg, seating area.
Permit Reviews
Permit Number - DP19-0190
Permit Status: Approved
Permit Description: SITE/GRADING - Hotel Congress, stage, storage bldg, seating area.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/15/2020 | DEV PKG - RESUBMITTAL | 05/15/2020 | COMPLETED |
| 07/11/2019 | DEV PKG - OK TO SUBMIT | 08/12/2019 | COMPLETED |
| 07/17/2020 | DEV PKG - RESUBMITTAL | 08/17/2020 | COMPLETED |
| 08/12/2019 | DEV PKG | 09/25/2019 | COMPLETED |
| 08/31/2020 | DEV PKG - RESUBMITTAL | 09/02/2020 | COMPLETED |
Outstanding Inspections
Permit Status: Approved
Permit Number: DP19-0190
Permite Description: SITE/GRADING - Hotel Congress, stage, storage bldg, seating area.
Total Outstanding Inspections - 9
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2022 | PDSD Site/Engineering Division - Landscaping | N/A | Not Ready | |
| 10/26/2022 | PDSD Site/Engineering Division - NPPO | N/A | Not Ready | |
| 10/27/2022 | ENGR Engineering Final | N/A | Not Ready | |
| 10/26/2022 | SITE - Stormwater Follow-up | N/A | Not Ready | |
| 10/27/2022 | ENGR Grading Final | N/A | Not Ready | |
| 10/26/2022 | SITE - Stormwater Final Inspection | N/A | Not Ready | |
| 10/26/2022 | SITE - Stormwater Setup and Controls | N/A | Not Ready | |
| 10/26/2022 | PDSD Engineering Division Pre-Construction SITE | N/A | Not Ready | |
| 10/27/2022 | COT - ENGR - Signage Final | N/A | Not Ready |