Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Development Package
Apply Date:
03/25/2019
Applicant:
Description:
GRADING - Biolife Plasma Services Center, (clearing/grubbing).

Permit Reviews

Permit Number - DP19-0072
Permit Status: Complete
Permit Description: GRADING - Biolife Plasma Services Center, (clearing/grubbing).
Start Date Submittal Complete Date Status  
02/21/2019 DEV PKG - OK TO SUBMIT (GRADING ONLY) 03/25/2019 COMPLETED Review Details
04/01/2019 DEV PKG - OK TO SUBMIT (GRADING ONLY) 04/01/2019 COMPLETED Review Details
04/01/2019 DEV PKG - OK TO SUBMIT (GRADING ONLY) 04/03/2019 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP19-0072
Permit Description: GRADING - Biolife Plasma Services Center, (clearing/grubbing).
Total Completed Inspections - 9
Date Description Inspector Results Comments
10/28/2019 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 10/28/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
10/28/2019 PDSD Site/Engineering Division - NPPO Passed {Activity date: 10/28/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
10/28/2019 ENGR Engineering Final Passed {Activity date: 10/28/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
10/28/2019 SITE - Stormwater Follow-up Passed {Activity date: 10/28/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
10/28/2019 ENGR Grading Final Passed {Activity date: 10/28/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
10/28/2019 SITE - Stormwater Final Inspection Passed {Activity date: 10/28/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
10/28/2019 SITE - Stormwater Setup and Controls Passed {Activity date: 10/28/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
10/28/2019 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 10/28/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
10/28/2019 COT - ENGR - Signage Final Passed {Activity date: 10/28/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }

Documents

File Name Document Type  
PERMIT.PDF DOCUMENTS VIEW
CONTRACTOR LETTER.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
SWPPP REPORT.PDF DOCUMENTS VIEW
1-4 OF 4.PDF DEVELOPMENT PACKAGE VIEW