Permit: DP19-0028
Permit Details
Apply Date:
02/04/2019
Applicant:
CLINT ELDER
Description:
ROUGH GRADING/NPPO - SHARP
Permit Reviews
Permit Number - DP19-0028
Permit Status: Complete
Permit Description: ROUGH GRADING/NPPO - SHARP
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/04/2019 | DEV PKG - OK TO SUBMIT (GRADING ONLY) | 02/04/2019 | COMPLETED |
02/04/2019 | GRADING | 02/05/2019 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP19-0028
Permit Description: ROUGH GRADING/NPPO - SHARP
Total Completed Inspections - 9
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/07/2019 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 02/07/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by CBELL1 - Met on site with project manager went over and Nppo. And stormwater controls. Asked to be called in every other week for Stormwater controls.} | |
09/22/2020 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 09/22/2020; Status: Approved; Inspector: rledonne; Comment: Entered by RLEDONN1 - } ; {Activity date: 03/04/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by SFLORES2 - City water doing pressure test on reclaimed irrigation water. Working on grouted riprap in basins in parking area.} | |
09/22/2020 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 09/22/2020; Status: Approved; Inspector: rledonne; Comment: Entered by RLEDONN1 - } | |
09/22/2020 | SITE - Stormwater Follow-up | Passed | {Activity date: 09/22/2020; Status: Approved; Inspector: rledonne; Comment: Entered by RLEDONN1 - } ; {Activity date: 08/27/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by JSCHNEI2 - Continue. No concerns at this time.} ; {Activity date: 08/21/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by JSCHNEI2 - Continue. No concerns at this time.} ; {Activity date: 08/07/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - Continue. No concerns at this time.} ; {Activity date: 07/31/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - Continue. No concerns at this time. } ; {Activity date: 07/17/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by JSCHNEI2 - Continue. No concerns at this time} ; {Activity date: 07/09/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - Continue. No concerns at this time.} ; {Activity date: 06/18/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - Continue. No concerns at this time.} ; {Activity date: 03/07/2019; Status: Continued; Inspector: RLEDONN1; Comment: Entered by RLEDONN1 - GRADING CONTACTOR NOT ON SITE. CONTROLS NEED TO BE INSTALLED.} ; {Activity date: 02/20/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - FOREMAN NOT ON SITE.} |
|
09/22/2020 | ENGR Grading Final | Passed | {Activity date: 09/22/2020; Status: Approved; Inspector: rledonne; Comment: Entered by RLEDONN1 - } | |
09/22/2020 | SITE - Stormwater Final Inspection | Passed | {Activity date: 09/22/2020; Status: Approved; Inspector: rledonne; Comment: Entered by RLEDONN1 - } | |
09/22/2020 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 09/22/2020; Status: Approved; Inspector: rledonne; Comment: Entered by RLEDONN1 - } ; {Activity date: 01/23/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - Provide washout for concrete trucks make corrections to controls around site.} | |
09/22/2020 | COT - ENGR - Signage Final | Passed | {Activity date: 09/22/2020; Status: Approved; Inspector: rledonne; Comment: Entered by RLEDONN1 - } | |
04/06/2022 | ENGR Engineering Final | Passed | {Activity date: 04/06/2022; Status: Approved; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - FINAL APPROVED} ; {Activity date: 04/15/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VLEON1 - } |