| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/19/2020 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 11/19/2020; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
| 11/19/2020 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 11/19/2020; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
| 11/19/2020 | ENGR Engineering Final | Passed | {Activity date: 11/19/2020; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
| 11/19/2020 | SITE - Stormwater Follow-up | Passed | {Activity date: 11/19/2020; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
| 11/19/2020 | ENGR Grading Final | Passed | {Activity date: 11/19/2020; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
| 11/19/2020 | SITE - Stormwater Final Inspection | Passed | {Activity date: 11/19/2020; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
| 11/19/2020 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 11/19/2020; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
| 11/19/2020 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 11/19/2020; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
| 11/19/2020 | COT - ENGR - Signage Final | Passed | {Activity date: 11/19/2020; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } |