Permit: DP18-0204
Permit Details
Apply Date:
08/22/2018
Applicant:
Robert Page
Description:
SITE - McGraw's Restaurant expansion.
Permit Reviews
Permit Number - DP18-0204
Permit Status: Issued
Permit Description: SITE - McGraw's Restaurant expansion.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/22/2018 | DEV PKG - OK TO SUBMIT (GRADING ONLY) | 08/22/2018 | COMPLETED |
08/22/2018 | SITE and/or GRADING | 10/05/2018 | COMPLETED |
10/05/2018 | RESUB - SITE/GRADING ALL | 11/13/2018 | COMPLETED |
11/13/2018 | RESUB - SITE and/or GRADING | 11/05/2021 | COMPLETED |
12/06/2021 | DEV PKG - OK TO SUBMIT | 12/13/2021 | COMPLETED |
12/13/2021 | REVISION - - 1ST | 02/14/2022 | COMPLETED |
Outstanding Inspections
Permit Status: Issued
Permit Number: DP18-0204
Permite Description: SITE - McGraw's Restaurant expansion.
Total Outstanding Inspections - 11
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - FCON - Sprinkler - Final | N/A | Not Ready | |
10/26/2022 | COT - FCON - Fire - Final | N/A | Not Ready | |
10/11/2023 | PDSD Site/Engineering Division - NPPO | N/A | Not Ready | Reschedule I was at the project early this morning gates are locked so I came back later this afternoon and the gates are still locked. Contacts gonna have to reschedule. |
10/11/2023 | ENGR Engineering Final | N/A | Not Ready | Reschedule I was at the project early this morning gates are locked so I came back later this afternoon and the gates are still locked. Contacts gonna have to reschedule. |
10/11/2023 | SITE - Stormwater Final Inspection | N/A | Not Ready | Reschedule I was at the project early this morning gates are locked so I came back later this afternoon and the gates are still locked. Contacts gonna have to reschedule. |
10/31/2023 | PDSD Site/Engineering Division - Landscaping | N/A | Not Ready | No one on site at this time |
10/31/2023 | SITE - Stormwater Follow-up | N/A | Complete (Recurring) | No concerns at this time |
10/31/2023 | ENGR Grading Final | N/A | Partial Pass | Still under construction no one on site as of today |
10/31/2023 | SITE - Stormwater Setup and Controls | N/A | Complete (Recurring) | No concerns at this time still under construction |
10/31/2023 | PDSD Engineering Division Pre-Construction SITE | N/A | Not Ready | No one on site at this time still under construction |
10/31/2023 | COT - ENGR - Signage Final | N/A | Not Ready | Still under construction no one on site at this time |