Permit Details

Status:
Complete
Type:
Development Package
Address NEW:
9251 S EISENHOWER RD
Apply Date:
06/21/2018
Applicant:
Description:
SITE AND GRADING - SANTA CRUZ WATER PRODUCTION FACILITY

Permit Reviews

Permit Number - DP18-0154
Permit Status: Complete
Permit Description: SITE AND GRADING - SANTA CRUZ WATER PRODUCTION FACILITY
Start Date Submittal Complete Date Status  
06/21/2018 SITE and/or GRADING 06/22/2018 COMPLETED Review Details
06/22/2018 SITE and/or GRADING 07/24/2018 COMPLETED Review Details
08/26/2019 SITE and/or GRADING 08/26/2019 COMPLETED Review Details

Conditions

Permit Number - DP18-0154
Permit Status: Complete
Permit Description: SITE AND GRADING - SANTA CRUZ WATER PRODUCTION FACILITY
Date Description Comments
07/23/2018 A complete SWPPP manual for the project is to be provided during the initial pre-construction meeting.

Completed Inspections

Permit Status: Complete
Permit Number: DP18-0154
Permit Description: SITE AND GRADING - SANTA CRUZ WATER PRODUCTION FACILITY
Total Completed Inspections - 9
Date Description Inspector Results Comments
12/05/2019 PDSD Site/Engineering Division - NPPO Passed {Activity date: 12/05/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - }
12/05/2019 ENGR Engineering Final Passed {Activity date: 12/05/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - }
12/05/2019 SITE - Stormwater Follow-up Passed {Activity date: 12/05/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - }
12/05/2019 ENGR Grading Final Passed {Activity date: 12/05/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - }
12/05/2019 SITE - Stormwater Final Inspection Passed {Activity date: 12/05/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - }
12/05/2019 SITE - Stormwater Setup and Controls Passed {Activity date: 12/05/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - }
12/05/2019 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 12/05/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } ; {Activity date: 12/03/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - I spoke with Jeremy with PCL at 602-228-3037. I requested that he schedule inspections from his development package permit and provide approved civil drawings for The site inspections required.} ; {Activity date: 08/30/2019; Status: Denied; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Contractor needs to call in for a preconstruction meeting.}
12/05/2019 COT - ENGR - Signage Final Passed {Activity date: 12/05/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - }
12/11/2019 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 12/11/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - A friend}