Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Development Package
Address:
1121 E 7TH ST
Address NEW:
1121 E 7TH ST
Apply Date:
02/23/2018
Applicant:
Description:
E SITE/GRADING - The Graymont.

Permit Reviews

Permit Number - DP18-0050
Permit Status: Complete
Permit Description: E SITE/GRADING - The Graymont.
Start Date Submittal Complete Date Status  
01/18/2019 DEV PKG - REVISION 01/24/2019 COMPLETED Review Details
02/23/2018 DEV PKG - OK TO SUBMIT 02/28/2018 COMPLETED Review Details
03/01/2018 DEV PKG 05/30/2018 COMPLETED Review Details
05/30/2018 DEV PKG - RESUBMITTAL 06/29/2018 COMPLETED Review Details
06/12/2019 DEV PKG - REVISION 06/28/2019 COMPLETED Review Details
06/29/2018 DEV PKG - RESUBMITTAL 07/27/2018 COMPLETED Review Details
09/03/2019 DEV PKG - OK TO SUBMIT 09/06/2019 COMPLETED Review Details
12/07/2018 DEV PKG - REVISION 01/09/2019 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP18-0050
Permit Description: E SITE/GRADING - The Graymont.
Total Completed Inspections - 10
Date Description Inspector Results Comments
07/31/2019 PDSD Site/Engineering Division - NPPO Passed {Activity date: 07/31/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - }
07/31/2019 SITE - Stormwater Follow-up Passed {Activity date: 07/31/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - }
07/31/2019 SITE - Stormwater Final Inspection Passed {Activity date: 07/31/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - }
07/31/2019 SITE - Stormwater Setup and Controls Passed {Activity date: 07/31/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - }
08/02/2019 COT - FCON - Fire - Final Passed {Activity date: 08/02/2019; Status: Approved; Inspector: JPEELDAVIS; Comment: Entered by JPEELDA1 - }
08/05/2019 COT - ENGR - Signage Final Passed {Activity date: 08/05/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - }
08/07/2019 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 08/07/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - }
08/13/2019 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 08/13/2019; Status: Approved; Inspector: DROBERTS; Comment: Entered by DMERANZ1 - }
09/09/2019 ENGR Engineering Final Passed {Activity date: 09/09/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } ; {Activity date: 08/13/2019; Status: Not ready for Inspection; Inspector: DROBERTS; Comment: Entered by DMERANZ1 - COMPLETE SIDEWALK AND WILL VARIFY ROOF DRAINAGE} ; {Activity date: 08/02/2019; Status: Denied; Inspector: DROBERTS; Comment: Entered by DROBERT5 - I CONTACTED STEVE SHIELDS AND JOHN VAN WINKLE ABOUT THE INSPECTION AND THEY HAVE AGREED THAT THE ENGINEER NEEDS TO COME DOWNTOWN AND DISCUSS WITH THEM WHAT ARE THE CHANGES THAT ARE ACCEPTABLE. THE MINIMUM 3 FOOT SIDEWALK FOR THIS SITE IS A REQUIREMENT THAT CAN NOT BE OVERLOOKED SINCE THIS WAS A REQUIREMENT FOR THE DSMR. I HAVE ADVISED THEM OF ALL OTHER CHANGES AND ISSUES THAT HAVE BEEN TO MY ATTENTION, THERE MAYBE OTHERS OUT ON THE SITE THAT I AM NOT AWARE OF.} ; {Activity date: 08/02/2019; Status: Denied; Inspector: DROBERTS; Comment: Entered by DROBERT5 - I WAS ADVISED BY RON LEDONNE THAT THERE ARE ISSUES ON THIS SITE IN REGARDS TO THE SIDE WALKS BEING LESS THAN MINIMUM CODE. THIS AFTERNOON I WALKED THROUGH THE SITE AND MET WITH THE CONTRACTOR TO DISCUSS SOME OF THE ISSUES THAT I SEE:
1) THE SIDEWALKS ON THE INTERIOR ARE SPECIFIED TO BE AT A MINIMUM OF 3 FEET WIDE. DUE TO WAY THAT THE BUILDINGS HAVE BEEN CONSTRUCTED THEY ARE NOT ABLE TO PROVIDE THE MINIMUM 3 FOOT.
2) THE HANDICAP PARKING SPACE AND ACCESS AISLE DOES NOT MEET THE MAXIMUM OF 2% CROSS SLOPE. THEIS WILL NEED TO BE CORRECTED PRIOR TO SCHEDULING THE FINAL INSPECTION FOR THIS SITE.
3) ALONG THE EXTERIOR OF THE BUILDINGS AT VARIOUS LOCATIONS, ROOF DRAINAGE IS BEING DEPOSITED DIRECTLY ONTO THE SIDE WALKS. THEY WILL NEED TO CONTACT THE ENGINEER OF RECORD TO DECIDE HOW THESE AREAS CAN BE DRAIN CORRECTLY SO THAT IT DOES NOT INTERFERE WITH THE PEDESTRIAN PATHWAY.
4) AT THE NORTHWEST CORNER OF THIS SITE A SET OF STEPS HAVE BEEN INSTALLED IN THE AREA THAT LEADS TO THE TRASH RECEPTICLES FOR THIS SITE. I WILL ASK STEVE SHIELDS WHAT IS THE DETERMINATION FOR THESE STEPS.
5) COMPLETE THE SITE AFTER THE ENGINEER OF RECORD HAS MADE A DETERMINATION FOR ALL OF THE QUESTIONS THAT HAVE BEEN ASKED FOR THIS SITE.} ; {Activity date: 07/31/2019; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - Walked site with GC. Roof drains going over sidewalk in multiple locations. ADA parking over 2%.not able to check all sidewalks debris and dirt on sidewalks. Ramp on north west corner of property over 8.3%. Complete all landscaping and staking trees per detail. Complete all work on approved plans. List may not be complete.}
09/10/2019 ENGR Grading Final Passed {Activity date: 09/10/2019; Status: Approved; Inspector: DROBERTS; Comment: Entered by JVWINKL1 - }

Documents

File Name Document Type  
None LETTER OF COMPLETION VIEW
1-11 OF 11.PDF DEVELOPMENT PACKAGE VIEW
PERMIT.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
INSPECTION JOB CARD.PDF DOCUMENTS VIEW
CONTRACTOR LETTER.PDF DOCUMENTS VIEW
DRAINAGE_STATEMENT.PDF DOCUMENTS VIEW
GEOTECH.PDF DOCUMENTS VIEW
LOT_COMBO_APPROVAL_LETTER.PDF DOCUMENTS VIEW
1_DP18-0050_GRAYMONT_ADDRESSING.PDF DOCUMENTS VIEW
REVISION_LETTER.PDF DOCUMENTS VIEW
RESPONSE_LETTER.PDF DOCUMENTS VIEW
RECORDED_LOT_1_WARRANTY_DEED.PDF DOCUMENTS VIEW
RECORDED_LOT_2_WARRANTY_DEED.PDF DOCUMENTS VIEW
RECORDED_RECIPROCAL_ACCESS_AGREEMENT.PDF DOCUMENTS VIEW
SUMMARY OF CHANGES.PDF DOCUMENTS VIEW
REVISION_LETTER, 09.03.19.PDF DOCUMENTS VIEW