Permit: DP18-0042
Permit Details
Apply Date:
02/13/2018
Applicant:
Brandy Burke
Description:
E SITE/GRADE - DUTCH BROTHERS WILMOT
Permit Reviews
Permit Number - DP18-0042
Permit Status: Complete
Permit Description: E SITE/GRADE - DUTCH BROTHERS WILMOT
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/13/2018 | DEV PKG - OK TO SUBMIT | 02/22/2018 | COMPLETED |
| 02/22/2018 | DEV PKG | 03/23/2018 | COMPLETED |
| 04/02/2018 | DEV PKG - RESUBMITTAL | 04/17/2018 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP18-0042
Permit Description: E SITE/GRADE - DUTCH BROTHERS WILMOT
Total Completed Inspections - 7
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/15/2018 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 05/15/2018; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO PRE-CON CALLED IN. INSPECTION DONE AFTER SITE HAD BEEN ROUGH GRADED AND SOME CURBING IN PLACE} ; {Activity date: 04/20/2018; Status: Partial Approval; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 08/23/2018 | SITE - Stormwater Follow-up | Passed | {Activity date: 08/23/2018; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 08/21/2018; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS.} ; {Activity date: 08/15/2018; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS.} ; {Activity date: 08/08/2018; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.} ; {Activity date: 07/18/2018; Status: Continued; Inspector: RLEDONN1; Comment: Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.} ; {Activity date: 07/13/2018; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.} ; {Activity date: 07/02/2018; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS WORKING ON BUILDING.} ; {Activity date: 06/21/2018; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.} | |
| 08/23/2018 | ENGR Grading Final | Passed | {Activity date: 08/23/2018; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
| 08/23/2018 | SITE - Stormwater Final Inspection | Passed | {Activity date: 08/23/2018; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
| 08/23/2018 | COT - ENGR - Signage Final | Passed | {Activity date: 08/23/2018; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 08/16/2018; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
| 09/12/2018 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 09/12/2018; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 09/04/2018; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
| 09/12/2018 | ENGR Engineering Final | Passed | {Activity date: 09/12/2018; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 08/23/2018; Status: Partial Approval; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - OK FOR TCO ONLY. COMPLET ALL WORK ON AP PLANS.} |