Permit: DP18-0003
Permit Details
Status:
Complete
Type:
Development Package
Address:
4333 E SPEEDWAY BL
Address NEW:
4333 E SPEEDWAY BL
Apply Date:
01/05/2018
Applicant:
Marty Magelli
Description:
SITE
Permit Reviews
Permit Number - DP18-0003
Permit Status: Complete
Permit Description: SITE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/05/2018 | SITE and/or GRADING | 01/05/2018 | COMPLETED |
Outstanding Inspections
Permit Status: Complete
Permit Number: DP18-0003
Permite Description: SITE
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/13/2019 | ENGR Engineering Final | N/A | Complete (Recurring) | {Activity date: 03/13/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 03/13/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO TRACK OUT AT THIS TIME.} ; {Activity date: 03/06/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO TRACK OUT AT THIS TIME.} ; {Activity date: 02/25/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO TRACK OUT AT THIS TIME.} ; {Activity date: 02/19/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO TRACK OUT AT THIS TIME.} ; {Activity date: 12/06/2018; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - ADA PARKING ON EAST SIDE OF BUILDINGS #2 & #3.} |
Completed Inspections
Permit Status: Complete
Permit Number: DP18-0003
Permit Description: SITE
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/14/2021 | ENGR Grading Final | Passed | {Activity date: 07/14/2021; Status: Approved; Inspector: RELEFANTE; Comment: Entered by RSALDAT1 - Continued. Note, inspector recommends changing status to final approved as the required inspection was approved.} |