Permit: DP17-0132
Permit Details
Apply Date:
06/12/2017
Applicant:
Description:
SITE
Permit Reviews
Permit Number - DP17-0132
Permit Status: Complete
Permit Description: SITE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/12/2017 | SITE and/or GRADING | 02/07/2018 | ACTIVE |
06/12/2017 | SITE and/or GRADING | 06/12/2017 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP17-0132
Permit Description: SITE
Total Completed Inspections - 1
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/20/2018 | ENGR Engineering Final | Passed | {Activity date: 03/20/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 03/16/2018; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - SITE IS NOT READY AT THIS TIME. CURRENTLY THEY ARE STILL WORKING ON THE INSTALLATION OF THE TUBING FOR THE TANKS. SCHEDULE ALL OF THE REMAINING INSPECTIONS FOR PERMIT T17CM04471, AND ENSURE ALL THE SITE WORK IS DONE THEN CALL FOR A RENSPECTION OF THIS SITE.} |