Permit: DP17-0122
Permit Details
Apply Date:
05/25/2017
Applicant:
Description:
TENTATIVE PLAT - LEE STREET LOTS 1-4
Permit Reviews
Permit Number - DP17-0122
Permit Status: Issued
Permit Description: TENTATIVE PLAT - LEE STREET LOTS 1-4
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/25/2017 | DEV PKG - OK TO SUBMIT | 06/01/2017 | COMPLETED |
06/01/2017 | TENTATIVE PLAT REVIEW | 06/30/2017 | COMPLETED |
09/01/2017 | TENTATIVE PLAT REVIEW | 10/06/2017 | COMPLETED |
11/07/2017 | RESUBMITTAL - CDRC - TENTATIVE PLAT REVIEW | 12/08/2017 | ACTIVE |
Outstanding Inspections
Permit Status: Issued
Permit Number: DP17-0122
Permite Description: TENTATIVE PLAT - LEE STREET LOTS 1-4
Total Outstanding Inspections - 6
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/19/2021 | SITE - Stormwater Follow-up | N/A | Complete (Recurring) | {Activity date: 08/19/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Residential construction work in progress.} ; {Activity date: 11/30/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by PAHUMAD1 - Continue. No concerns at this time. } ; {Activity date: 11/23/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by PAHUMAD1 - Continue. No concerns at this time.} ; {Activity date: 11/18/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by PAHUMAD1 - Continue. No concerns at this time.} ; {Activity date: 10/29/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by PAHUMAD1 - Continue. No concerns at this time.} ; {Activity date: 10/22/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - Continue. No concerns at this time.} ; {Activity date: 09/10/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by JSCHNEI2 - Continue. No concerns at this time.} ; {Activity date: 09/01/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by JSCHNEI2 - Continue. No concerns at this time.} ; {Activity date: 08/24/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by JSCHNEI2 - Continue. No concerns at this time.} ; {Activity date: 07/30/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by JSCHNEI2 - Continue. No concerns at this time.} ; {Activity date: 07/10/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by JSCHNEI2 - Continue. No concerns at this time.} ; {Activity date: 06/18/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - Continue. No concerns at this time.} ; {Activity date: 05/14/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - No concerns at this time.} ; {Activity date: 05/04/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - Continue. GC not on site. Need to add controls west of site along wash. 09185 grading intermediate. Continue. No grading activity on site at this time.} ; {Activity date: 06/04/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - NO CONCERNS AT THIS TIME} ; {Activity date: 05/02/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by CBELL1 - No concerns at this time.} ; {Activity date: 04/10/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by CBELL1 - Controls have been added around stockpile and on west side of site} ; {Activity date: 03/06/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO ACTIVITY ON SITE AT THIS TIME.} ; {Activity date: 01/02/2019; Status: Continued; Inspector: RLEDONN1; Comment: Entered by RLEDONN1 - no activity on site.} ; {Activity date: 10/29/2018; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS.} ; {Activity date: 08/20/2018; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS.} |
10/27/2022 | ENGR Grading Final | N/A | Not Ready | |
10/26/2022 | SITE - Stormwater Setup and Controls | N/A | Not Ready | |
01/02/2024 | PDSD Site/Engineering Division - Landscaping | N/A | Not Ready | No landscape areas as per plan can be found. |
01/02/2024 | PDSD Site/Engineering Division - NPPO | N/A | Not Ready | Not confirmed |
01/02/2024 | SITE - Stormwater Final Inspection | N/A | Not Ready | Can not confirm that storm water is completed |
Completed Inspections
Permit Status: Issued
Permit Number: DP17-0122
Permit Description: TENTATIVE PLAT - LEE STREET LOTS 1-4
Total Completed Inspections - 5
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/06/2018 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 08/06/2018; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
11/01/2023 | ENGR Grading Final | Passed | SFR COMPLETE ready for final |
|
11/01/2023 | SITE - Stormwater Setup and Controls | Passed | ||
01/02/2024 | ENGR Engineering Final | Passed | ||
01/02/2024 | COT - ENGR - Signage Final | Passed |