Permit: DP17-0094
Permit Details
Apply Date:
04/19/2017
Applicant:
David Gary Gerovac
Description:
SITE/GRADING/SWPP - MATH & SCIENCE ACADEMYOriginal approval 5/25/2017 (10 pages)1st Revision
Permit Reviews
Permit Number - DP17-0094
Permit Status: Complete
Permit Description: SITE/GRADING/SWPP - MATH & SCIENCE ACADEMYOriginal approval 5/25/2017 (10 pages)1st Revision
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/12/2018 | REVISION - - 3RD | 02/13/2018 | COMPLETED |
04/19/2017 | DEV PKG - OK TO SUBMIT | 04/19/2017 | COMPLETED |
04/19/2017 | DEV PKG | 05/23/2017 | COMPLETED |
05/23/2017 | DEV PKG - RESUBMITTAL | 05/26/2017 | COMPLETED |
06/27/2017 | DEV PKG - REVISION | 11/22/2017 | COMPLETED |
08/15/2018 | DEV PKG - REVISION | 08/16/2018 | ACTIVE |
11/22/2017 | REVISION - - 2ND | 11/27/2017 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP17-0094
Permit Description: SITE/GRADING/SWPP - MATH & SCIENCE ACADEMYOriginal approval 5/25/2017 (10 pages)1st Revision
Total Completed Inspections - 9
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/12/2017 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 06/12/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
09/12/2018 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 09/12/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
09/12/2018 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 09/12/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
09/12/2018 | SITE - Stormwater Follow-up | Passed | {Activity date: 09/12/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 10/06/2017; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - 1) PLACE ADDITIONAL BMP'S AROUND THE STOCKPILE THAT IS LOCATED WEST OF THIS SITE. 2) CLEANUP ALL TRACKED OUT MATERIAL AS NEEDED ON THE PRIVATE PROPERTY WEST OF THIS SITE.} ; {Activity date: 08/07/2017; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - NO CONCERNS AT THIS TIME FOR THIS SITE, NO RAIN HAS HAPPENED IN THE PAST WEEK AND THE SITE IS IN GOOD SHAPE. THIS SITE WILL NEED TO BE SCHEDULED IN 2 WEEKS OR EARLIER IF THEY HAVE OVER 1/2 IN OF RAIN BEFORE THEN.} ; {Activity date: 06/29/2017; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - WALKED SITE WITH GC WENT OVER HDPE PIPING IN BASINS.} |
|
09/12/2018 | ENGR Grading Final | Passed | {Activity date: 09/12/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
09/12/2018 | SITE - Stormwater Final Inspection | Passed | {Activity date: 09/12/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
09/12/2018 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 09/12/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 03/20/2018; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - NDO CONCERNS AT THIS TIME ALL CONTROLS APPEAR TO BE WORKING AS DESIGNED.} ; {Activity date: 06/12/2017; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - INSTALL ALL SWPPP CONTOLS PER AP PLANS.} | |
09/12/2018 | COT - ENGR - Signage Final | Passed | {Activity date: 09/12/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
09/13/2018 | ENGR Engineering Final | Passed | {Activity date: 09/13/2018; Status: Approved; Inspector: bbenedo1; Comment: Entered by BBENEDO1 - } ; {Activity date: 09/13/2018; Status: Approved; Inspector: bbenedo1; Comment: Entered by BBENEDO1 - } |