Permit: DP17-0021
Permit Details
Apply Date:
01/24/2017
Applicant:
Kevin Paulus
Description:
Econolend Tucson Parking Lot reconfiguration
Permit Reviews
Permit Number - DP17-0021
Permit Status: Complete
Permit Description: Econolend Tucson Parking Lot reconfiguration
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/24/2017 | SITE and/or GRADING | 01/24/2017 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP17-0021
Permit Description: Econolend Tucson Parking Lot reconfiguration
Total Completed Inspections - 9
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/24/2017 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 02/24/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 02/24/2017 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 02/24/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 02/24/2017 | SITE - Stormwater Follow-up | Passed | {Activity date: 02/24/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 02/24/2017 | SITE - Stormwater Final Inspection | Passed | {Activity date: 02/24/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 02/24/2017 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 02/24/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 02/24/2017 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 02/24/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 02/24/2017 | COT - ENGR - Signage Final | Passed | {Activity date: 02/24/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 03/16/2017 | ENGR Engineering Final | Passed | {Activity date: 03/16/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - DROPPED OFF HARD COPY OF INSP REQUEST} ; {Activity date: 03/14/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 02/24/2017; Status: Denied; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) PROVIDE HC PARKING THAT MEETS ADA 2) PROVIDE WHEEL STOPS FOR PARKING SPACES SHOWN ON THE APPROVED PLANS. 3) PROVIDE A HC PARKING SIGN FOR THE HC PARKING SPACE} |
|
| 06/20/2017 | RSBU - Building Final | Passed | {Activity date: 06/20/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } |