Permit: DP17-0003
Permit Details
Status:
Complete
Type:
Development Package
Address:
2542 N WOODS END PL
Address NEW:
2542 N WOODS END PL
Apply Date:
01/04/2017
Applicant:
Christi Swenson
Description:
NEW SFR T17CM00058
Permit Reviews
Permit Number - DP17-0003
Permit Status: Complete
Permit Description: NEW SFR T17CM00058
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/04/2017 | GRADING | 01/04/2017 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP17-0003
Permit Description: NEW SFR T17CM00058
Total Completed Inspections - 10
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/10/2017 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 01/10/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
| 01/17/2017 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 01/17/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 01/13/2017; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
| 06/08/2017 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 06/08/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 06/08/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
| 06/08/2017 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 06/08/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
| 06/08/2017 | SITE - Stormwater Follow-up | Passed | {Activity date: 06/08/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
| 06/08/2017 | ENGR Grading Final | Passed | {Activity date: 06/08/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
| 06/08/2017 | SITE - Stormwater Final Inspection | Passed | {Activity date: 06/08/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
| 06/08/2017 | COT - ENGR - Signage Final | Passed | {Activity date: 06/08/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
| 06/15/2017 | ENGR Engineering Final | Passed | {Activity date: 06/15/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 06/08/2017; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - KEYNOTE #1 ON AP PLANS SIDEWALK SCUPPER NOT INSTALLED.} | |
| 06/20/2017 | RSBU - Building Final | Passed | {Activity date: 06/20/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } |