Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/28/2017 | REVISION - SITE | 03/28/2017 | COMPLETED |
06/06/2017 | REVISION - SITE | 06/06/2017 | ACTIVE |
12/28/2016 | SITE and/or GRADING | 12/29/2016 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP16-0237
Permit Description: AZ REHAB CLINIC
Total Completed Inspections - 10
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/26/2017 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 04/26/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
04/26/2017 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 04/26/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
04/26/2017 | SITE - Stormwater Follow-up | Passed | {Activity date: 04/26/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
04/26/2017 | ENGR Grading Final | Passed | {Activity date: 04/26/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
04/26/2017 | SITE - Stormwater Final Inspection | Passed | {Activity date: 04/26/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
04/26/2017 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 04/26/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
04/26/2017 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 04/26/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
04/26/2017 | COT - ENGR - Signage Final | Passed | {Activity date: 04/26/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
05/04/2017 | ENGR Engineering Final | Passed | {Activity date: 05/04/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 04/27/2017; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - MET WITH THE CONTRACTOR AND LOOKED OVER THE 2 ACCESS RAMPS FOR THIS SITE. THEY HAVE CONSTRUCTED A BARRIER RAIL ON BOTH SIDES OF THE RAMPS, BUT THEY ALSO NEED A HANDRAIL. I SHOWED THEM THE HANDRAIL AND BUMPER REQUIREMENTS IN THE ICC A117.1-2009. I HAVE ADVISED THEM THAT THEY WILL NEED TO INSTALL THE HANDRAIL AND THE BUMPER GUARD WITH A CLEARANCE OF LESS THAN 4 INCHES PRIOR TO CALLING IN THIS INSPECTION FOR THE FINAL.} ; {Activity date: 04/26/2017; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - THIS SITE HAS BEEN CHECKED FOR EVERYTHING BUT THE HANDICAP ACCESS FROM THE TO LOCATIONS WITHIN THE PARKING LOTS. THESE AREAS WILL BE CHECKED TOMORROW WITH A LEVEL TO ENSURE THAT THEY ARE COMPLIANT WITH THE MAXIMUM SLOPE VALUES FOR CROSS SLOPE AND FOR RUNNING SLOPES.} | |
06/28/2017 | RSBU - Building Final | Passed | {Activity date: 06/28/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } |