Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: DP16-0201
Permit Details
Apply Date:
11/14/2016
Applicant:
Lisa Bowers
Description:
SITE/GRADING
Permit Reviews
Permit Number - DP16-0201
Permit Status: Complete
Permit Description: SITE/GRADING
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/24/2017 | RESUB - SITE and/or GRADING | 03/13/2017 | COMPLETED |
11/14/2016 | DEV PKG - OK TO SUBMIT | 11/21/2016 | COMPLETED |
11/21/2016 | SITE and/or GRADING | 02/24/2017 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP16-0201
Permit Description: SITE/GRADING
Total Completed Inspections - 9
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/25/2017 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 09/25/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - MET WITH CHRIS AND DISCUSSED THE PLANS FOR THIS SITE. CURRENTLY THE LOCATION THAT THEY ARE LOOKING AT FOR THE HANDICAP ACCES PARKING LOCATIONA AND ACCESS AISLE CROSSES OVER THE SITE DRAINAGE CHANNEL. I HAVE ASKED FOR HIM TO MEET WITH HIS ARCHITECT AND PROPPOSE A SOLUTION FOR WHAT WAS NOT DRAWN CORRECTLY WHEN THEY SUBMITTED THE PLANS FOR THIS SITE.} | |
11/27/2017 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 11/27/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
11/27/2017 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 11/27/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
11/27/2017 | ENGR Engineering Final | Passed | {Activity date: 11/27/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
11/27/2017 | SITE - Stormwater Follow-up | Passed | {Activity date: 11/27/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 09/25/2017; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - NO CONCERNS AT THIS TIME} | |
11/27/2017 | ENGR Grading Final | Passed | {Activity date: 11/27/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 09/25/2017; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - THE PLANS DO NOT REFLECT THE CURRENT FIELD CONDITIONS, A DRAINAGE SWALE CROSSES OVER THE AREA OF THE ACCESS AISLE AND PARKING SPOT. MODIFICATIONS WILL NEED TO BE MADE TO THE PLAN LOCATIONS FOR THIS AREA. ONCE THEY ARE SUBMITTED CONTACT ME SO THAT I CAN VERIFY THAT THE C URRENT CONDITIONS HAVE BEEN SHOWN IN THEIR CURRENT STATE.} | |
11/27/2017 | SITE - Stormwater Final Inspection | Passed | {Activity date: 11/27/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
11/27/2017 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 11/27/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
11/27/2017 | COT - ENGR - Signage Final | Passed | {Activity date: 11/27/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } |