Permit Details

Status:
Issued
Type:
Development Package
Address:
3131 E LEE ST
Address NEW:
3131 E LEE ST
Apply Date:
11/02/2016
Applicant:
GEORGE HOLGUIN
Description:
SITE/GRADINGOriginally approved 5/5/2017 (9 pages)

Permit Reviews

Permit Number - DP16-0191
Permit Status: Issued
Permit Description: SITE/GRADINGOriginally approved 5/5/2017 (9 pages)
Start Date Submittal Complete Date Status  
02/22/2017 DEV PKG - RESUBMITTAL 04/04/2017 COMPLETED Review Details
04/05/2017 DEV PKG - RESUBMITTAL 05/05/2017 COMPLETED Review Details
09/10/2018 DEV PKG - REVISION 09/10/2018 COMPLETED Review Details
11/02/2016 DEV PKG - OK TO SUBMIT 11/02/2016 COMPLETED Review Details
11/02/2016 SITE and/or GRADING 12/07/2016 COMPLETED Review Details

Outstanding Inspections

Permit Status: Issued
Permit Number: DP16-0191
Permite Description: SITE/GRADINGOriginally approved 5/5/2017 (9 pages)
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
10/27/2022 ENGR Engineering Final N/A Not Ready

Completed Inspections

Permit Status: Issued
Permit Number: DP16-0191
Permit Description: SITE/GRADINGOriginally approved 5/5/2017 (9 pages)
Total Completed Inspections - 8
Date Description Inspector Results Comments
05/24/2017 SITE - Stormwater Setup and Controls Passed {Activity date: 05/24/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - SEDIMENT CONTROLS HAVE BEEN INSTALLED} ; {Activity date: 05/17/2017; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - THEY HAVE INSTALLED WADDLE MATERIAL ALONG THE SOUTH SIDE OF THE PROJECT ALONG THE CONSTRUCTION FENCE, BUT IT NEEDS TO BE RE-INSTALLED PER THE APPROVED PLANS, SLIGHTLY BURIED AND PROPERLY STAKED.}
05/24/2017 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 05/24/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 05/17/2017; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - SITE WORK HAS STARTED WITH THE CLEARING OF THE SITE. THE CONTRACTOR HAS ADVISED ME THAT HE WOPULD NOT BE ABLE TO SAVE ALL THE TREES THAT WERE CALLED OUT ON THE NPPO. I HAVE ADVISED JOHN WITH DURAZO CONSTRUCTION THAT THEY WILL HAVE TO CONTACT JOSEPH LINVILLE AND SEE WHAT THEY NEED TO DO TO MITIGATE THE PLANTS THAT THEY COULDN'T SAVE.}
10/10/2018 COT - ENGR - Signage Final Passed {Activity date: 10/10/2018; Status: Approved; Inspector: BBENEDON; Comment: Entered by CBELL1 - } ; {Activity date: 05/17/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - THESE INSPECTIONS ARE NOT REQUIRED FOR THIS SITE.}
10/17/2018 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 10/17/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
10/17/2018 PDSD Site/Engineering Division - NPPO Passed {Activity date: 10/17/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 10/10/2018; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by CBELL1 - previous notes} ; {Activity date: 05/17/2017; Status: Not ready for Inspection; Inspector: DROBERTS; Comment: Entered by DROBERT5 - THIS WORK WILL BE CHECKED ONCE IT HAS BEEN DETERMINED WHAT MITIGATION WORK IS REQUIRED.}
10/17/2018 SITE - Stormwater Follow-up Passed {Activity date: 10/17/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 05/17/2017; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - NO CONCERNS AT THIS TIME}
10/17/2018 SITE - Stormwater Final Inspection Passed {Activity date: 10/17/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 10/10/2018; Status: Approved; Inspector: BBENEDON; Comment: Entered by CBELL1 - }
09/20/2023 ENGR Engineering Final Passed

Documents

File Name Document Type  
001_CVR.TIF DEVELOPMENT PACKAGE VIEW
002_SD-1.TIF DEVELOPMENT PACKAGE VIEW
003_C-1.TIF DEVELOPMENT PACKAGE VIEW
004_LS-1.TIF DEVELOPMENT PACKAGE VIEW
005_LS-2.TIF DEVELOPMENT PACKAGE VIEW
006_LS-3.TIF DEVELOPMENT PACKAGE VIEW
007_LS-4.TIF DEVELOPMENT PACKAGE VIEW
008_LS-5.TIF DEVELOPMENT PACKAGE VIEW
009_LS-6.TIF DEVELOPMENT PACKAGE VIEW
001_SP-1.TIF DEVELOPMENT PACKAGE VIEW
JAS DRAINAGE STATEMENT 9-6-16_OPTIMIZE.PDF DOCUMENTS VIEW
RESPONSE-040217-COMPLETE.PDF DOCUMENTS VIEW
TRASH ENCLOSURE EMAIL.PDF DOCUMENTS VIEW
DEVELOPMENT PACKAGE_ADDRESSING (1).PDF DOCUMENTS VIEW
None DOCUMENTS VIEW