Permit: DP15-0208
Permit Details
Apply Date:
11/30/2015
Applicant:
David Gary Gerovac
Description:
SITE/GRADE - WESTERNER - Major IID project. Review conditions. Lot split with new build and TI
Permit Reviews
Permit Number - DP15-0208
Permit Status: Complete
Permit Description: SITE/GRADE - WESTERNER - Major IID project. Review conditions. Lot split with new build and TI
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/15/2016 | DEV PKG - RESUBMITTAL | 02/19/2016 | COMPLETED |
| 01/24/2018 | DEV PKG - REVISION | 06/13/2019 | COMPLETED |
| 02/19/2016 | DEV PKG - RESUBMITTAL | 10/25/2016 | COMPLETED |
| 10/25/2016 | DEV PKG - RESUBMITTAL | 12/28/2016 | COMPLETED |
| 11/30/2015 | DEV PKG - OK TO SUBMIT | 11/30/2015 | COMPLETED |
| 11/30/2015 | DEV PKG | 01/15/2016 | COMPLETED |
| 12/28/2016 | DEV PKG - RESUBMITTAL | 01/18/2017 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP15-0208
Permit Description: SITE/GRADE - WESTERNER - Major IID project. Review conditions. Lot split with new build and TI
Total Completed Inspections - 9
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/21/2018 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 09/21/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
| 09/21/2018 | SITE - Stormwater Follow-up | Passed | {Activity date: 09/21/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
| 09/21/2018 | ENGR Grading Final | Passed | {Activity date: 09/21/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
| 09/21/2018 | SITE - Stormwater Final Inspection | Passed | {Activity date: 09/21/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
| 09/21/2018 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 09/21/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
| 09/21/2018 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 09/21/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
| 09/21/2018 | COT - ENGR - Signage Final | Passed | {Activity date: 09/21/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
| 09/26/2018 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 09/26/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 09/21/2018; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - OK FOR A TCO AT THIS TIME FOR THE BUILDING, FINAL NOT TO BE GIVEN TILL ALL OF THE REMAINING SITE WORK HAS BEEN COMPLETED, OR TILL REVISED DRAWINGS HAVE BEEN PROVIDE SHOWING THE ITEMS THAT ARE NOT COMPLETE AT THIS TIME. THE CONTRACTOR HAS PLANTER BOXES THAT HAVE NOT BEEINSTALLED ALONG WITH BICYCLE RACKS, THESE WILL BE INSTALLED AT A LATER DATE.} |
|
| 09/26/2018 | ENGR Engineering Final | Passed | {Activity date: 09/26/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 09/21/2018; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - OK FOR A TCO AT THIS TIME FOR THE BUILDING, FINAL NOT TO BE GIVEN TILL ALL OF THE REMAINING SITE WORK HAS BEEN COMPLETED, OR TILL REVISED DRAWINGS HAVE BEEN PROVIDE SHOWING THE ITEMS THAT ARE NOT COMPLETE AT THIS TIME. THE CONTRACTOR HAS PLANTER BOXES THAT HAVE NOT BEEINSTALLED ALONG WITH BICYCLE RACKS, THESE WILL BE INSTALLED AT A LATER DATE.} |