Permit: DP15-0033
Permit Details
Apply Date:
03/02/2015
Applicant:
Lisa Bowers
Description:
SITE - ILLEGAL PETE'S PACKAGE RECONFIGURATION Originally approved 8/21/2015Revision 1 was a re
Permit Reviews
Permit Number - DP15-0033
Permit Status: Complete
Permit Description: SITE - ILLEGAL PETE'S PACKAGE RECONFIGURATION Originally approved 8/21/2015Revision 1 was a re
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/28/2017 | DEV PKG - REVISION | 03/14/2017 | COMPLETED |
03/02/2015 | DEV PKG - OK TO SUBMIT | 03/02/2015 | COMPLETED |
03/03/2015 | DEV PKG | 04/22/2015 | COMPLETED |
04/23/2015 | DEV PKG - RESUBMITTAL | 06/17/2015 | COMPLETED |
06/17/2015 | DEV PKG - RESUBMITTAL | 08/06/2015 | COMPLETED |
08/06/2015 | DEV PKG - RESUBMITTAL | 08/08/2015 | COMPLETED |
08/08/2015 | DEV PKG - RESUBMITTAL | 08/21/2015 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP15-0033
Permit Description: SITE - ILLEGAL PETE'S PACKAGE RECONFIGURATION Originally approved 8/21/2015Revision 1 was a re
Total Completed Inspections - 3
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/14/2017 | ENGR Engineering Final | Passed | {Activity date: 09/14/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 09/06/2017; Status: Partial Approval; Inspector: pyg; Comment: Entered by PGEHLEN1 - Cert letter in SIRE. 207 waiver still pending.} ; {Activity date: 08/23/2017; Status: Partial Approval; Inspector: MRUSSO; Comment: Entered by DROBERT5 - PARTIAL APPROVAL FOR ENG FINAL 1) PROVIDE CERT STATEMENT FROM THE ENG OF RECORD 2) REMOVE THE NOTICE DATED 4/20/17 CALL FOR RE-INSPECTION} ; {Activity date: 12/07/2015; Status: Denied; Inspector: MRUSSO; Comment: Entered by DROBERT5 - COMPLETE LANDSCAPING, SITE WORK, AND GRADING PER THE APPROVED PLAN.} |
|
09/14/2017 | ENGR Grading Final | Passed | {Activity date: 09/14/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 08/01/2017; Status: Partial Approval; Inspector: MRUSSO; Comment: Entered by DROBERT5 - ENCLOSURE PAD RE-BAR INSTALLED PER APPROVED STD DETAIL - OK TO POUR CONCRETE} ; {Activity date: 07/18/2017; Status: Partial Approval; Inspector: MRUSSO; Comment: Entered by DROBERT5 - RE-BAR LAY OUT AND FOOTINGS WERE INSTALLED PER APPROVED PLANS} ; {Activity date: 07/14/2017; Status: Correction Required; Inspector: DROBERTS; Comment: Entered by DROBERT5 - THE CONTRACTOR IS NOT READY AT THIS TIME FOR THIS INSPECTION, COMPLETE THE REBAR PLACEMENT PER THE CITY DETAIL AND CLL THIS INSPECTION IN FOR NEXT WEEK.} | |
09/14/2017 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 09/14/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 08/01/2017; Status: Partial Approval; Inspector: MRUSSO; Comment: Entered by DROBERT5 - ENCLOSURE PAD RE-BAR INSTALLED PER APPROVED STD DETAIL - OK TO POUR CONCRETE} ; {Activity date: 07/25/2017; Status: Partial Approval; Inspector: MRUSSO; Comment: Entered by DROBERT5 - PROGRESS ON TRASH ENCLOSURE WALL. GROUTING OF CELLS TO COME - TAKE PICS OF GROUTING} ; {Activity date: 07/18/2017; Status: Partial Approval; Inspector: MRUSSO; Comment: Entered by DROBERT5 - RE-BAR LAY OUT AND FOOTINGS WERE INSTALLED PER APPROVED PLANS} ; {Activity date: 07/14/2017; Status: Correction Required; Inspector: DROBERTS; Comment: Entered by DROBERT5 - THE CONTRACTOR IS NOT READY AT THIS TIME FOR THIS INSPECTION, COMPLETE THE REBAR PLACEMENT PER THE CITY DETAIL AND CLL THIS INSPECTION IN FOR NEXT WEEK.} |