Permit Details

Status:
Complete
Type:
Development Package
Address NEW:
7760 E SPEEDWAY BL
Apply Date:
05/09/2014
Applicant:
Description:
SITE/GRADING- EEGEE'S

Permit Reviews

Permit Number - DP14-0075
Permit Status: Complete
Permit Description: SITE/GRADING- EEGEE'S
Start Date Submittal Complete Date Status  
03/03/2015 REVISION - SITE 03/06/2015 ACTIVE Review Details
05/09/2014 DEV PKG - OK TO SUBMIT 05/09/2014 COMPLETED Review Details
05/09/2014 SITE and/or GRADING 07/22/2014 COMPLETED Review Details
07/22/2014 RESUB - SITE/GRADING ALL 03/03/2015 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP14-0075
Permit Description: SITE/GRADING- EEGEE'S
Total Completed Inspections - 7
Date Description Inspector Results Comments
05/15/2015 SITE - Stormwater Follow-up Passed {Activity date: 05/15/2015; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
05/15/2015 ENGR Grading Final Passed {Activity date: 05/15/2015; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
05/15/2015 SITE - Stormwater Final Inspection Passed {Activity date: 05/15/2015; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
05/15/2015 SITE - Stormwater Setup and Controls Passed {Activity date: 05/15/2015; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
05/15/2015 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 05/15/2015; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
05/22/2018 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 05/22/2018; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 05/15/2015; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - THE CONTRACTOR NEEDS TO COMPLETE THE INSTALLATION OF ALL THE PLANTS PRIOR TO CALLING IN FOR THE FINAL FOR THIS SITE.}
05/22/2018 ENGR Engineering Final Passed {Activity date: 05/22/2018; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 06/12/2015; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - COMPLET ALL NOTES FROM PAST INSPECTIONS.} ; {Activity date: 05/15/2015; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - COMPLETE ALL WORK ON THIS SITE, AND CLEAR ALL EXCESS MATERIAL PRIOR TO SCHEDULING FOR THE FINAL INSPECTION.}